19440 W SHENANGO DR 91356
Certificate Information: 19440 W SHENANGO DR 91356
- Application / Permit
- 20014-30000-03387
- Plan Check / Job No.
- B20WL03394
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to the side of SFD to relocate kitchen and laundry room, add storage room and family room. (N) trellis over patio at rear.
- Permit Issued
- Issued on 3/15/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/14/2020 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 8/21/2020 | APPLICANT |
| Plan Check Approved | 11/2/2023 | JOHNPAUL ISIP |
| Issued | 3/15/2024 | APPLICANT |
| CofO in Progress | 4/20/2026 | JOHN KIDWELL |
| Permit Finaled | 4/20/2026 | JOHN JANSON |
| CofO Issued | 4/20/2026 | JOHN JANSON |
| Permit Finaled | 4/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/10/2020 | BARTON HOLMES |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/5/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Psg Hardware & Supply; Lic. No.: 1079377-B | 10418 GLADE AVENUE CHATSWORTH, CA 91311 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/31/2025 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 7/31/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 7/31/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 8/6/2025 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 8/6/2025 | Approved | THOMAS FINNILA |
| Wood Frame | 8/6/2025 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | JOHN HAYES |
| Green Building Rough | 8/8/2025 | Approved | JOHN HAYES |
| Insulation | 8/8/2025 | Approved | JOHN HAYES |
| Drywall Nailing | 8/14/2025 | Approved | JOHN KIDWELL |
| Gas Test | 9/12/2025 | Approved | JOHN KIDWELL |
| Final | 11/10/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 11/10/2025 | Approved | MORRIS JACKSON |
| Green Building Final | 11/10/2025 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 11/10/2025 | Approved | MORRIS JACKSON |
| Final | 4/16/2026 | OK to Issue CofO | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 4/16/2026 | SGSOV Approved | JOHN KIDWELL |