6002 W ERNEST AVE 90034
Certificate Information: 6002 W ERNEST AVE 90034
- Application / Permit
- 20014-30000-03363
- Plan Check / Job No.
- B20WL03385
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1st & 2nd story ADU addition to (E) detached garage at rear of lot.
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 9/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/15/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 9/24/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| Plan Check Approved | 4/4/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 4/16/2021 | APPLICANT |
| CofO in Progress | 9/26/2022 | EVAN COOPER |
| Permit Finaled | 9/28/2022 | DANIEL ORRANTE |
| CofO Issued | 9/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 3/9/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/15/2021 | WALLIE JONG |
| Sewer availability | Cleared | 3/18/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/26/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Footing/Foundation/Slab | 7/26/2021 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Rough | 7/26/2021 | Corrections Issued | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 8/3/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 8/3/2021 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/9/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 8/9/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/9/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 10/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 10/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/27/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 10/27/2021 | Not Ready for Inspection | EVAN COOPER |
| MERV13>=Rough | 10/27/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/9/2021 | Corrections Issued | EVAN COOPER |
| Gas Test | 12/9/2021 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 12/9/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 12/9/2021 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 12/15/2021 | No Access for Inspection | EVAN COOPER |
| MERV13>=Rough | 12/15/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 12/16/2021 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/16/2021 | Approved | EVAN COOPER |
| Gas Test | 12/16/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 12/16/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | EVAN COOPER |
| Green Building Rough | 2/3/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/3/2022 | Partial Approval | EVAN COOPER |
| MERV13>=Rough | 2/3/2022 | Approved | EVAN COOPER |
| Insulation | 2/23/2022 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 2/23/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 3/29/2022 | Approved | EVAN COOPER |
| Insulation | 3/29/2022 | Approved | EVAN COOPER |
| Service/Power Release | 6/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Final | 8/15/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 8/15/2022 | Approved | EVAN COOPER |
| MERV13>=Final | 8/15/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 8/15/2022 | Approved | EVAN COOPER |
| Smoke Detectors | 8/15/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 8/16/2022 | Corrections Issued | EVAN COOPER |
| Final | 9/19/2022 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 9/19/2022 | Approved | ANDREW NAVE |
| Final | 9/26/2022 | OK to Issue CofO | EVAN COOPER |