8510-8512 S GLIDER AVE 90045

Certificate Information: 8510-8512 S GLIDER AVE 90045

Application / Permit
20014-30000-03332
Plan Check / Job No.
B20WL03345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Exterior and interior remodel of an existing duplex. Addition to both units.
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Corrected on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/11/2020 JAHANSHAH POURHASSAN
Corrections Issued 8/11/2020 JAHANSHAH POURHASSAN
Plan Check Approved 9/17/2020 MANUEL GARCIA
No Progress 11/12/2020 JASON JANGADA
Building Plans Picked Up 11/13/2020 APPLICANT
Plan Check Approved 2/8/2021 RICHARD GARCIA
Issued 11/10/2021 APPLICANT
CofO in Progress 12/30/2022 BOBBY KEY
CofO Issued-Status Void 1/18/2023 DANIEL ORRANTE
Permit Finaled-Status Void 1/18/2023 DANIEL ORRANTE
Re-Activate Permit 3/3/2026 DANIEL ORRANTE
Permit Finaled 3/12/2026 RICHARD STEINBACH
CofO Corrected 3/12/2026 RICHARD STEINBACH
Permit Finaled 3/12/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/8/2020 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/9/2020 OSCAR GUTIERREZ
Specific Plan Cleared 2/1/2021 VALERIA CEJA

Contact Information

Contractor Owner-Builder       ,
Engineer Kamkar,, Albert; Lic. No.: C38311 12340 SANTA MONICA BLVD 236      SANTA MONICA, CA 90025

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2022 Approved BOBBY KEY
Footing/Foundation/Slab 3/9/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 4/4/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 4/8/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 4/11/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 5/10/2022 Not Ready for Inspection BOBBY KEY
Green Building Rough 5/10/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 5/10/2022 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Conditional Approval BOBBY KEY
PLUMBING-Rough 5/17/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval BOBBY KEY
Insulation 6/14/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 8/26/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 8/26/2022 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 8/26/2022 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 9/14/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Corrections Issued BOBBY KEY
Green Building Rough 9/14/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 9/14/2022 Approved BOBBY KEY
ELECTRICAL-Rough 9/16/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Approved BOBBY KEY
HVAC-Rough 9/16/2022 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 9/27/2022 Conditional Approval BOBBY KEY
Green Building Rough 9/27/2022 Approved BOBBY KEY
HVAC-Rough 9/27/2022 Approved BOBBY KEY
Interior/Exterior Lathing 9/27/2022 Partial Approval BOBBY KEY
Insulation 9/29/2022 Corrections Issued BOBBY KEY
Insulation 10/4/2022 Approved BOBBY KEY
Drywall Nailing 10/12/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 12/28/2022 Approved BOBBY KEY
ELECTRICAL-Final 12/28/2022 Corrections Issued BOBBY KEY
Final 12/28/2022 Not Ready for Inspection BOBBY KEY
Green Building Final 12/28/2022 Approved BOBBY KEY
HVAC-Final 12/28/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 12/28/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 12/28/2022 Approved BOBBY KEY
ELECTRICAL-Final 12/30/2022 Approved BOBBY KEY
Final 12/30/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 12/30/2022 Approved BOBBY KEY
PLUMBING-Final 12/30/2022 Approved BOBBY KEY
Service/Power Release 12/30/2022 Approved BOBBY KEY