842 W 18TH ST 90731

Certificate Information: 842 W 18TH ST 90731

Application / Permit
20014-30000-03299
Plan Check / Job No.
B20WL03312
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) detached garage to create two new accessory dwelling units (590 SF each, 1180 SF total) per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)¹, (d)¹, and (g). (E) garage to remain.
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/11/2020 JASON JANGADA
Corrections Issued 8/11/2020 JASON JANGADA
Applicant returned to address corrections 1/28/2021 MARJAN SHENASI
Plan Check Approved 2/26/2021 MARJAN SHENASI
Building Plans Picked Up 3/3/2021 APPLICANT
Issued 3/12/2021 APPLICANT
CofO in Progress 2/15/2022 ANSON MAGLASANG
Permit Finaled 2/17/2022 DEROLD HAUFF
CofO Issued 2/17/2022 DEROLD HAUFF
Permit Finaled 2/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 8/28/2020 CHINH DINH
Sewer availability Cleared 8/28/2020 CHINH DINH
Low Impact Development Cleared 1/8/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 1/13/2021 CHINH DINH
Hydrant and Access approval Cleared 1/21/2021 MATTHEW CRAIG
GPI Written Notices Cleared 2/25/2021 JASON JANGADA
Grading Pre-Inspection Cleared 2/25/2021 JASON JANGADA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2021 Partial Approval JOHN KLARIN
Underground Mechanical 5/6/2021 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 5/19/2021 Approved JOHN KLARIN
Grounding or Bonding 5/19/2021 Approved JOHN KLARIN
Light Gage Steel Frame 5/19/2021 Approved JOHN KLARIN
Wood Frame 7/15/2021 Partial Approval JOHN KLARIN
PLUMBING-Rough 7/28/2021 Partial Approval JOHN KLARIN
PLUMBING-Rough 8/13/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 8/27/2021 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 8/31/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/3/2021 Approved ANSON MAGLASANG
Green Building Rough 9/3/2021 Approved ANSON MAGLASANG
Insulation 9/3/2021 Approved ANSON MAGLASANG
Drywall Nailing 9/29/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 9/29/2021 Approved JOHN KLARIN
ELECTRICAL-Final 10/27/2021 Corrections Issued ANSON MAGLASANG
HVAC-Final 12/1/2021 Corrections Issued JOHN KLARIN
PLUMBING-Final 12/1/2021 Approved JOHN KLARIN
Smoke Detectors 12/1/2021 Approved JOHN KLARIN
Underground Mechanical 12/1/2021 Approved JOHN KLARIN
PLUMBING-Final 12/7/2021 Approved JOHN KLARIN
ELECTRICAL-Final 12/20/2021 Not Ready for Inspection ANSON MAGLASANG
HVAC-Final 12/20/2021 Not Ready for Inspection ANSON MAGLASANG
Service/Power Release 12/20/2021 Not Ready for Inspection ANSON MAGLASANG
Final 1/27/2022 Corrections Issued ANSON MAGLASANG
Gas Test 1/27/2022 Approved ANSON MAGLASANG
Green Building Final 1/27/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Approved ANSON MAGLASANG
ELECTRICAL-Final 2/11/2022 Approved ANSON MAGLASANG
Final 2/11/2022 OK to Issue CofO ANSON MAGLASANG
Service/Power Release 2/11/2022 Approved ANSON MAGLASANG