1401 N DOHENY DR 90069
Certificate Information: 1401 N DOHENY DR 90069
- Application / Permit
- 20014-30000-03239
- Plan Check / Job No.
- B20WL03269
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition (443 sf) to (e) 2-story SFD to add a bedroom and bathroom
- Permit Issued
- Issued on 11/18/2021
- Issuing Office
- Current Status
- Issued on 11/18/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | REZA HAGHIGHAT |
| Corrections Issued | 8/10/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 8/19/2020 | TARIK SAOUD |
| Plan Check Approved | 11/4/2021 | REZA HAGHIGHAT |
| Issued | 11/18/2021 | APPLICANT |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/16/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 9/16/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 9/16/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 9/16/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 9/16/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2020 | THOMAS LANG |
| Sewer availability | Cleared | 9/17/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/21/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 11/4/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | Ceci Clarke Inc; Lic. No.: 1040135-B | 444 ARNEILL ROAD CAMARILLO, CA 93010 |
| Engineer | Alemozafar,, Jilla; Lic. No.: C36047 | 728 WESTBOURNE DRIVE WEST HOLLYWOOD, CA 90069 |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/14/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/1/2022 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 6/1/2022 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 9/13/2022 | Approved | RAUL BARAJAS |
| Insulation | 9/16/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/27/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/27/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/2/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/10/2023 | Approved | RAUL BARAJAS |
| Final | 5/10/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 5/10/2023 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 5/10/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 5/10/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 5/10/2023 | Approved | RAUL BARAJAS |
| Final | 5/26/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 5/26/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 6/28/2023 | Partial Inspection | RAUL BARAJAS |