4285 S LINDBLADE DR 90066
Certificate Information: 4285 S LINDBLADE DR 90066
- Application / Permit
- 20014-30000-03149
- Plan Check / Job No.
- B20WL03199
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to existing SFD.
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofO Issued on 7/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | JASON JANGADA |
| Corrections Issued | 7/31/2020 | JASON JANGADA |
| Plan Check Approved | 8/18/2020 | MANUEL GARCIA |
| Issued | 2/3/2021 | APPLICANT |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| CofO in Progress | 6/30/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 7/3/2023 | DANIEL ORRANTE |
| CofO Issued | 7/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2020 | KATHLEEN LEE |
| Sewer availability | Cleared | 8/6/2020 | KATHLEEN LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2020 | KATHLEEN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guirguis,, Diaa S; Lic. No.: C40731 | 1320 19TH ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/12/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/23/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/23/2021 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/26/2021 | Approved | ENRIQUE MIRELES |
| Sewer | 3/26/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/19/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/19/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 5/26/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/4/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/4/2021 | Approved | AMY COLIN |
| Shower Pan | 7/13/2021 | Partial Inspection | ADAM ESCOTO |
| Shower Pan | 8/4/2021 | Approved | ENRIQUE MIRELES |
| Final | 10/1/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 10/1/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/1/2021 | Approved | ENRIQUE MIRELES |
| Final | 4/8/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Final | 4/29/2022 | Conditional Approval | PATRICK QUALEY |
| ELECTRICAL-Final | 6/30/2023 | Approved | JESUS RODRIGUEZ |
| Final | 6/30/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 6/30/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/30/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/30/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/30/2023 | Approved | JESUS RODRIGUEZ |