1630-1632 S HOLT AVE 90035
Certificate Information: 1630-1632 S HOLT AVE 90035
- Application / Permit
- 20014-30000-03100
- Plan Check / Job No.
- B20WL03157
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Remodel and 2nd Story Addition to an (E) 1-Story SFD and Convert (E) S.F.D to Duplex per Assembly Bill 2097 Parking Not Required for New Unit
- Permit Issued
- Issued on 7/26/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | DAVID CASTILLO |
| Corrections Issued | 8/25/2020 | DAVID CASTILLO |
| Quality Review Completed | 8/26/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 3/9/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/11/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/1/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/23/2023 | DAVID CASTILLO |
| Building Plans Picked Up | 3/1/2023 | APPLICANT |
| Plan Check Approved | 3/31/2023 | DAVID CASTILLO |
| Issued | 7/26/2023 | APPLICANT |
| CofO in Progress | 4/22/2026 | WILBER ROSALES |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
| CofO Issued | 4/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2022 | CINDY QI |
| Sewer availability | Cleared | 8/1/2022 | CINDY QI |
| Low Impact Development | Cleared | 10/5/2022 | DEBORA LEITE |
| Hydrant and Access approval | Cleared | 10/14/2022 | LAVEON RIDER |
| Roof/Waste drainage to street | Cleared | 11/4/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: C64144 | 20016 LULL ST WINNETKA, CA 91306 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Barrier | 9/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Subgrade | 9/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/3/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 11/3/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 11/3/2023 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Reinforced Masonry Frame | 7/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Approved | MEL KHACHATOURIAN |
| Pre-Inspection | 7/24/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/20/2024 | Corrections Issued | ARAM AVEDISIAN |
| Pre-Inspection | 9/24/2024 | Partial Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 10/11/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 10/11/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/11/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Reinforced Masonry Frame | 10/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 12/4/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 2/14/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/14/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/24/2025 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 2/24/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 3/7/2025 | Approved | REGINA MENDEZ |
| Special/Order Compliance | 6/13/2025 | Approved | EVAN COOPER |
| Deputy Steel/Welding | 8/13/2025 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/14/2025 | Corrections Issued | EVAN COOPER |
| Final | 8/14/2025 | Corrections Issued | EVAN COOPER |
| Gas Test | 8/14/2025 | Approved | EVAN COOPER |
| Green Building Final | 8/14/2025 | Approved | EVAN COOPER |
| HVAC-Final | 8/14/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 8/14/2025 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/14/2025 | Approved | EVAN COOPER |
| Final | 2/27/2026 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 4/9/2026 | Approved | WILBER ROSALES |
| Final | 4/9/2026 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 4/9/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 4/9/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 4/22/2026 | Approved | WILBER ROSALES |