3677 S OCEAN VIEW AVE 90066

Certificate Information: 3677 S OCEAN VIEW AVE 90066

Application / Permit
20014-30000-03096
Plan Check / Job No.
B20WL03152
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 STORY ADDITION W/ ATTACHED GARAGE TO S.F.R.
Permit Issued
Issued on 12/22/2020
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 FELIPE HERNANDEZ
Corrections Issued 8/20/2020 FELIPE HERNANDEZ
Quality Review Completed 8/26/2020 TARIK SAOUD
Applicant returned to address corrections 11/5/2020 FELIPE HERNANDEZ
Applicant returned to address corrections 11/24/2020 FELIPE HERNANDEZ
Plan Check Approved 11/24/2020 FELIPE HERNANDEZ
Issued 12/22/2020 APPLICANT
Building Plans Picked Up 12/22/2020 APPLICANT
CofO in Progress 7/25/2022 JOHNNY MIRANDA
Permit Finaled 8/2/2022 DANIEL ORRANTE
CofO Issued 8/2/2022 DANIEL ORRANTE
Permit Finaled 8/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 9/22/2020 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 10/6/2020 NIKTA MOUSAVI
Permit Cleared 10/6/2020 NIKTA MOUSAVI
Hydrant and Access approval Cleared 10/19/2020 KURT CORRAL
Low Impact Development Cleared 10/20/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 10/26/2020 NIKTA MOUSAVI
Sewer availability Cleared 10/26/2020 NIKTA MOUSAVI
GPI Written Notices Cleared 11/24/2020 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 11/24/2020 FELIPE HERNANDEZ

Contact Information

Architect Genoist,, Bertrand; Lic. No.: C36796 2606 S BARRINGTON AVE UNIT A      LOS ANGELES, CA 90064
Contractor Genoist Bertrand; Lic. No.: 1068686-B 2606 S BARRINGTON AVE      LOS ANGELES, CA 90064
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/8/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 2/8/2021 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 2/9/2021 Partial Approval RICHARD ROBLES
Excavation/Setback/Form/Re-Bar 2/17/2021 Approved RICHARD ROBLES
Deputy Steel/Welding 2/24/2021 Conditional Approval RICHARD ROBLES
Deputy Other (see comments) 3/1/2021 Conditional Approval RICHARD ROBLES
Footing/Foundation/Slab 3/4/2021 Approved RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 4/3/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 6/3/2021 Approved EVAN COOPER
HVAC-Rough 6/3/2021 Approved EVAN COOPER
PLUMBING-Rough 6/3/2021 Approved EVAN COOPER
Interior/Exterior Lathing 8/24/2021 Partial Approval EVAN COOPER
Shower Pan 8/24/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 8/26/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 8/26/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/26/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/2/2021 Approved OGANES TARAKHCHYAN
Insulation 9/2/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 9/10/2021 Conditional Approval SHAVONNE ESPINOZA
Drywall Nailing 9/15/2021 Approved EVAN COOPER
Interior/Exterior Lathing 10/7/2021 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 12/20/2021 Corrections Issued EVAN COOPER
Gas Test 1/6/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 1/6/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 1/6/2022 Not Ready for Inspection JOHNNY MIRANDA
Gas Test 1/13/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 1/13/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 1/31/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 2/9/2022 Approved JOHNNY MIRANDA
HVAC-Final 2/9/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 2/22/2022 Approved JOHNNY MIRANDA
Final 4/6/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 4/6/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 4/6/2022 Approved JOHNNY MIRANDA
Final 6/3/2022 Corrections Issued JOHNNY MIRANDA
Final 7/25/2022 OK to Issue CofO JOHNNY MIRANDA