4330 W 60TH ST 90043

Certificate Information: 4330 W 60TH ST 90043

Application / Permit
20014-30000-03005
Plan Check / Job No.
B20WL03062
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition to rear of (E) 1-story SFD.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 8/17/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/25/2020 TARIK SAOUD
Plan Check Approved 11/18/2020 VLADIMIR ARUTYUNYAN
Issued 11/24/2020 APPLICANT
Building Plans Picked Up 12/1/2020 APPLICANT
CofO in Progress 7/7/2021 FREDDIE RIVERA
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/2/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 9/11/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/14/2020 THOMAS LANG
Sewer availability Cleared 9/14/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 2/22/2021 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/26/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 3/1/2021 Approved FREDDIE RIVERA
Shower Pan 3/9/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 3/17/2021 Approved FREDDIE RIVERA
Deputy Wood Construction 3/26/2021 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 4/30/2021 Approved FREDDIE RIVERA
Green Building Rough 4/30/2021 Approved FREDDIE RIVERA
Insulation 4/30/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/30/2021 Partial Approval FREDDIE RIVERA
Wood Frame 4/30/2021 Approved FREDDIE RIVERA
Drywall Nailing 5/11/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 5/11/2021 Partial Approval SABAS ALONSO
Shower Pan 5/11/2021 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/18/2021 Approved SABAS ALONSO
Shower Pan 5/18/2021 Approved SABAS ALONSO
Final 6/24/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 6/24/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 6/24/2021 Not Ready for Inspection FREDDIE RIVERA
Final 7/6/2021 OK to Issue CofO FREDDIE RIVERA
Green Building Final 7/6/2021 Approved FREDDIE RIVERA
Smoke Detectors 7/6/2021 Approved FREDDIE RIVERA