3936 S 6TH AVE 90008

Certificate Information: 3936 S 6TH AVE 90008

Application / Permit
20014-30000-02990
Plan Check / Job No.
B20WL03052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition to rear of (E) 2-story SFD, 1st floor: remodel kitchen, enlarge bathroom, relocate laundry room, 2nd floor: convert bathroom to master closet, enlarge one bathroom, relocate one bathroom.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
Issued on 1/12/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 JAHANSHAH POURHASSAN
Corrections Issued 7/28/2020 JAHANSHAH POURHASSAN
Plan Check Approved 8/13/2020 JAHANSHAH POURHASSAN
Issued 1/12/2021 APPLICANT
Building Plans Picked Up 1/13/2021 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Uribe Miguel; Lic. No.: 902301-B 645 W FLORAL DR      MONTEREY PARK, CA 91754

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2021 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/22/2021 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 2/4/2021 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 5/4/2021 Partial Approval DAVID FEILER
Service/Power Release 5/4/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/18/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/18/2021 Partial Inspection DAVID FEILER
Green Building Rough 5/18/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 5/18/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 5/18/2021 Not Ready for Inspection DAVID FEILER
Deputy Drilled-In Anchors 5/27/2021 Approved CALEB MEISTER
BUILDING-Rough-Frame 6/1/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 6/1/2021 Approved DAVID FEILER
Green Building Rough 6/1/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 6/1/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 6/1/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 6/7/2021 Partial Approval DAVID FEILER
Green Building Rough 6/7/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 7/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 7/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 7/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/27/2021 Conditional Approval DAVID FEILER
Green Building Rough 7/27/2021 Approved DAVID FEILER
HVAC-Rough 7/27/2021 Approved DAVID FEILER
Interior/Exterior Lathing 7/27/2021 Partial Approval DAVID FEILER
Deputy Wood Construction 7/28/2021 No Access for Inspection DAVID FEILER
Insulation 9/7/2021 Approved ALAN MORELOS
Drywall Nailing 9/28/2021 Approved DAVID FEILER
Interior/Exterior Lathing 9/28/2021 Not Ready for Inspection DAVID FEILER
Special/Order Compliance 9/28/2021 Partial Approval ASHLEY THOMPSON
Special/Order Compliance 8/7/2023 Approved JOSH MEISTER
Special/Order Compliance 3/26/2025 Partial Inspection LUIS CASTRO