22907 W CALVERT ST 91367
Certificate Information: 22907 W CALVERT ST 91367
- Application / Permit
- 20014-30000-02920
- Plan Check / Job No.
- B20WL02983
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- IN AN EXISTING ALQ... ADDITION TO AND CONVERSION OF AN ATTACHED GARAGE TO CREATE A NEW BEDROOM.
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- CofO Issued on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2020 | MARJAN SHENASI |
| Corrections Issued | 7/21/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/28/2020 | RICHARD GARCIA |
| Plan Check Approved | 11/12/2020 | RICHARD GARCIA |
| Issued | 12/1/2020 | APPLICANT |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| CofO in Progress | 8/17/2021 | TROY SANDERS |
| Permit Finaled | 11/18/2021 | JOHN JANSON |
| CofO Issued | 11/18/2021 | JOHN JANSON |
| Permit Finaled | 11/18/2021 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/30/2020 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 10/9/2020 | OSCAR GUTIERREZ |
Contact Information
| Architect | Diaz,, Richard E; Lic. No.: C34030 | 12619 EASTBROOK AVENUE DOWNEY, CA 90242 |
| Contractor | Bovee Construction Inc; Lic. No.: 702219-B | 21000 ALAMINOS DRIVE SAUGUS, CA 91350 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/19/2021 | Approved | TROY SANDERS |
| Deputy Wood Construction | 2/19/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 2/19/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 2/19/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 2/19/2021 | Approved | TROY SANDERS |
| Insulation | 3/11/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 3/15/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/15/2021 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 3/17/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/22/2021 | Approved | TROY SANDERS |
| Final | 4/22/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 4/22/2021 | Corrections Issued | TROY SANDERS |
| Green Building Rough | 4/22/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/22/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/22/2021 | Approved | TROY SANDERS |
| Final | 8/17/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/17/2021 | Approved | TROY SANDERS |
| Special/Order Compliance | 8/31/2021 | Corrections Issued | TROY SANDERS |