3802 W REVERE AVE 90039

Certificate Information: 3802 W REVERE AVE 90039

Application / Permit
20014-30000-02919
Plan Check / Job No.
B20WL02982
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/3/2020
Issuing Office
Current Status
CofO Issued on 6/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/20/2020 PARISA ZAHABI
Corrections Issued 7/20/2020 PARISA ZAHABI
Applicant returned to address corrections 9/10/2020 ALFREDO JARA
Plan Check Approved 10/19/2020 RICHARD GARCIA
Issued 11/3/2020 APPLICANT
Building Plans Picked Up 12/7/2020 APPLICANT
CofO in Progress 6/12/2023 HAMIK HARTOUNIAN
CofO Issued 6/25/2023 DEROLD HAUFF
Permit Finaled 6/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/3/2020 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 8/4/2020 JAMES KHO
Roof/Waste drainage to street Cleared 10/2/2020 JAMES KHO

Contact Information

Contractor D T K Builders Inc; Lic. No.: 813974-B 3035 N COOLIDGE AVE      LOS ANGELES, CA 90039
Engineer Lau,, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/2/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 3/8/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/12/2021 Approved SCOTT FINNILA
Special/Order Compliance 3/12/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 4/29/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 4/29/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/7/2021 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 5/20/2021 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 5/24/2021 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/21/2021 Partial Approval HAMIK HARTOUNIAN
Wood Frame 7/21/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/23/2021 Partial Approval HAMIK HARTOUNIAN
Deputy Steel/Welding 9/10/2021 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/14/2021 Conditional Approval HAMIK HARTOUNIAN
Structural Steel Frame 9/16/2021 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/21/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 1/14/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 2/1/2022 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 2/1/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 4/6/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 5/3/2022 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/17/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 5/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/17/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/13/2022 No Access for Inspection HAMIK HARTOUNIAN
HVAC-Rough 6/13/2022 No Access for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/14/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 7/12/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/18/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/2/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/16/2022 Approved HAMIK HARTOUNIAN
Insulation 8/16/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/16/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 9/8/2022 Approved HAMIK HARTOUNIAN
Shower Pan 11/3/2022 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 11/3/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/23/2022 Approved JOSEPH MCGARRY
Gas Test 3/7/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 4/12/2023 Corrections Issued SCOTT FINNILA
Final 4/12/2023 Corrections Issued SCOTT FINNILA
HVAC-Final 4/12/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Final 4/12/2023 Corrections Issued SCOTT FINNILA
Smoke Detectors 4/12/2023 Approved SCOTT FINNILA
ELECTRICAL-Final 4/28/2023 Approved ALIZAH MAYAGOITIA
Final 4/28/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 4/28/2023 Approved ALIZAH MAYAGOITIA
Green Building Final 4/28/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 4/28/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 4/28/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/28/2023 SGSOV Approved ALIZAH MAYAGOITIA
Final 6/12/2023 OK to Issue CofO HAMIK HARTOUNIAN