3866 S MCLAUGHLIN AVE 90066
Certificate Information: 3866 S MCLAUGHLIN AVE 90066
- Application / Permit
- 20014-30000-02918
- Plan Check / Job No.
- B20WL02980
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND ALTERATION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | SERGIO SILVA |
| Corrections Issued | 8/13/2020 | SERGIO SILVA |
| Quality Review Completed | 8/21/2020 | TARIK SAOUD |
| Building Plans Picked Up | 8/26/2020 | APPLICANT |
| Applicant returned to address corrections | 2/11/2021 | SERGIO SILVA |
| Plan Check Approved | 3/23/2021 | SERGIO SILVA |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 11/4/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 11/9/2022 | DANIEL ORRANTE |
| CofO Issued | 11/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 10/5/2020 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | NIKTA MOUSAVI |
| Permit | Cleared | 10/20/2020 | NIKTA MOUSAVI |
| Trees in Parkway | Cleared | 10/20/2020 | JOHN KIM |
| Sewer availability | Cleared | 10/26/2020 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/24/2020 | ANDRES COVARRUBIAS |
| Construction near power lines | Cleared | 1/9/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 1/19/2021 | NIKTA MOUSAVI |
| Green Code | Cleared | 3/23/2021 | SERGIO SILVA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/2/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/2/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Grading Pre-Inspection | 7/2/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Reinforced Concrete Frame | 7/2/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/19/2021 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 7/19/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 7/20/2021 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/22/2021 | Approved | ENRIQUE MIRELES |
| Grading Pre-Inspection | 7/22/2021 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 8/13/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 10/6/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/18/2021 | Approved | RYAN SALAZAR |
| Sewer | 10/18/2021 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/9/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/16/2021 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 11/23/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/23/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 11/23/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/23/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/30/2021 | Approved | JOHN KAYON |
| Green Building Rough | 11/30/2021 | Approved | JOHN KAYON |
| Interior/Exterior Lathing | 12/3/2021 | Partial Approval | KRISTEN CAUSEY |
| Shower Pan | 12/23/2021 | Approved | JOHN KAYON |
| Interior/Exterior Lathing | 1/5/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/4/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/4/2022 | Approved | ENRIQUE MIRELES |
| Final | 2/4/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/4/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/4/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/4/2022 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/4/2022 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 4/15/2022 | Partial Inspection | PATRICK QUALEY |
| Final | 11/3/2022 | OK to Issue CofO | JESUS RODRIGUEZ |