12018 N BRADFORD PL 91344

Certificate Information: 12018 N BRADFORD PL 91344

Application / Permit
20014-30000-02917
Plan Check / Job No.
B20WL02976
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-story ADU ground floor addition to existing 1-story SFD with attached garage.
Permit Issued
Issued on 4/1/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 FELIPE HERNANDEZ
Corrections Issued 8/12/2020 FELIPE HERNANDEZ
Quality Review Completed 8/19/2020 TARIK SAOUD
Applicant returned to address corrections 9/29/2020 FELIPE HERNANDEZ
Applicant returned to address corrections 11/20/2020 FELIPE HERNANDEZ
Applicant returned to address corrections 3/3/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 3/8/2021 FELIPE HERNANDEZ
Plan Check Approved 3/23/2021 FELIPE HERNANDEZ
Issued 4/1/2021 APPLICANT
Building Plans Picked Up 11/15/2022 APPLICANT
CofO in Progress 1/25/2023 SEAN HAUPT
No Progress 1/31/2023 SEAN HAUPT
CofO in Progress 2/6/2023 SEAN HAUPT
No Progress 5/9/2023 JOHN JANSON
CofO in Progress 4/22/2024 JOHN JANSON
Permit Finaled 4/22/2024 JOHN JANSON
CofO Issued 4/22/2024 JOHN JANSON
Permit Finaled 4/22/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/21/2020 LEE GUILBEAUX
Miscellaneous Cleared 9/21/2020 LEE GUILBEAUX
Watercourse Cleared 9/21/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/22/2020 LEE GUILBEAUX
Sewer availability Cleared 9/22/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/22/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 11/2/2020 MATTHEW CRAIG
Low Impact Development Cleared 2/17/2021 JORGE MEJIA LEMUS
GPI Written Notices Cleared 3/9/2021 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 3/9/2021 FELIPE HERNANDEZ
Roof/Waste drainage to street Cleared 3/17/2021 GUILLERMO PETRA

Contact Information

Contractor M S T Contractors Corporation; Lic. No.: 754023-B 18035 BURTON STREET      RESEDA, CA 91335
Engineer Haddad,, Alexander H; Lic. No.: C76351 3528 DUNE LN      LA VERNE, CA 91750

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/1/2021 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 10/7/2021 Partial Approval DAVID SCANTLIN
Pre-Inspection 10/7/2021 Approved DAVID SCANTLIN
Deputy Steel/Welding 11/3/2021 Conditional Approval MORRIS JACKSON
Pre-Inspection 11/8/2021 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval DAVID SCANTLIN
Deputy Wood Construction 2/14/2022 Conditional Approval MORRIS JACKSON
Rough-Elec/Plmb/HVAC 3/2/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/14/2022 Approved DAVID SCANTLIN
Green Building Rough 3/14/2022 Approved DAVID SCANTLIN
Drywall Nailing 3/21/2022 Approved DAVID SCANTLIN
Final 9/30/2022 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 9/30/2022 Approved DAVID SCANTLIN
Green Building Final 9/30/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 9/30/2022 Approved DAVID SCANTLIN
Final 1/24/2023 OK to Issue CofO SEAN HAUPT
Final 1/31/2023 Corrections Issued SEAN HAUPT
Final 2/7/2023 OK to Issue CofO SEAN HAUPT
Special/Order Compliance 2/22/2023 Corrections Issued DAVID SCANTLIN