8456 S VICKSBURG AVE 90045

Certificate Information: 8456 S VICKSBURG AVE 90045

Application / Permit
20014-30000-02899
Plan Check / Job No.
B20WL02966
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(e) garage to be converted to ADU
Permit Issued
Issued on 10/27/2020
Issuing Office
Current Status
CofO Issued on 4/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/15/2020 TARIK SAOUD
Corrections Issued 8/15/2020 TARIK SAOUD
Quality Review Completed 8/18/2020 CHIHARU SUZUKI
Plan Check Approved 10/19/2020 TARIK SAOUD
Issued 10/27/2020 APPLICANT
Building Plans Picked Up 11/2/2020 APPLICANT
CofO in Progress 4/20/2022 BOBBY KEY
Permit Finaled 4/21/2022 DANIEL ORRANTE
CofO Issued 4/21/2022 DANIEL ORRANTE
Permit Finaled 4/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 8/27/2020 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 10/2/2020 TRACY TATE
Sewer availability Cleared 10/2/2020 TRACY TATE
Low Impact Development Cleared 10/14/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 10/14/2020 TRACY TATE
Address approval Cleared 10/20/2020 TRACY TATE

Contact Information

Contractor Pure Builders Inc; Lic. No.: 757470-B 23966 CRAFTSMAN RD      CALABASAS, CA 91302
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/25/2020 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 12/1/2020 Approved JUAN VALENZUELA
Underground Mechanical 12/24/2020 Partial Approval DAVID HEINE
Underground Mechanical 12/28/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 1/6/2021 Not Ready for Inspection DAVID HEINE
Underground Mechanical 1/20/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/21/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 1/21/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 1/28/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/29/2021 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 2/1/2021 Not Ready for Inspection JUAN VALENZUELA
Shower Pan 2/1/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/3/2021 Partial Approval EVAN COOPER
Shower Pan 2/3/2021 Approved EVAN COOPER
PLUMBING-Rough 2/5/2021 Approved DAVID HEINE
BUILDING-Rough-Frame 3/10/2021 Approved JOHNNY MIRANDA
Green Building Rough 3/10/2021 Approved JOHNNY MIRANDA
Insulation 3/10/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/10/2021 Partial Approval JOHNNY MIRANDA
Drywall Nailing 3/19/2021 Approved DAVID HEINE
Gas Test 7/28/2021 Approved JESUS RODRIGUEZ
Final 10/1/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 10/1/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 10/1/2021 Approved BRENDAN LOONEY
Final 1/14/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Final 3/8/2022 Approved BOBBY KEY
Final 3/8/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 3/8/2022 Approved BOBBY KEY
PLUMBING-Final 3/8/2022 Approved BOBBY KEY
Final 4/20/2022 OK to Issue CofO BOBBY KEY