1336 W 22ND ST 90007
Certificate Information: 1336 W 22ND ST 90007
- Application / Permit
- 20014-30000-02835
- Plan Check / Job No.
- B20WL02899
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition of 2 story ADU to (E) detached garage at rear of lot.
- Permit Issued
- Issued on 11/7/2020
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 8/7/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 8/13/2020 | TARIK SAOUD |
| Plan Check Approved | 11/7/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 11/7/2020 | APPLICANT |
| Building Plans Picked Up | 11/9/2020 | APPLICANT |
| CofO in Progress | 3/1/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 8/13/2020 | KATIE DEBIASE |
| HPOZ | Cleared | 8/13/2020 | KATIE DEBIASE |
| Address approval | Cleared | 8/17/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 8/17/2020 | ELENA LOPEZ |
| "Q" conditions | Cleared | 8/20/2020 | RICHARD REASER |
| Low Impact Development | Cleared | 10/6/2020 | ORVAL HERNANDEZ-MARCI |
| ZI | Cleared | 10/6/2020 | SARAHI ORTEGA |
| Roof/Waste drainage to street | Cleared | 10/7/2020 | ELENA LOPEZ |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 1810 14TH STREET SUITE 204 SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 633 E 223RD ST B CARSON, CA 90745 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/16/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/16/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 11/18/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/18/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 11/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/23/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 12/23/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/23/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/28/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/28/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 12/28/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 12/28/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/30/2020 | Corrections Issued | SCOTT FINNILA |
| Insulation | 12/31/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/31/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/4/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/1/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 4/1/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 5/13/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 5/13/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 5/13/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/4/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 2/15/2022 | Partial Approval | KATHRYN BUTTERWORTH |