2938 S KELTON AVE 90064
Certificate Information: 2938 S KELTON AVE 90064
- Application / Permit
- 20014-30000-02776
- Plan Check / Job No.
- B20WL02831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2ND STORY ADDITION TO (E) 1-STORY SFD W/ATT.GARAGE; AND, ADDITION TO THE 1ST FLOOR.
- Permit Issued
- Issued on 11/11/2020
- Issuing Office
- Current Status
- CofO Issued on 6/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | PARISA ZAHABI |
| Corrections Issued | 8/7/2020 | PARISA ZAHABI |
| Quality Review Completed | 8/13/2020 | TARIK SAOUD |
| Building Plans Picked Up | 8/14/2020 | APPLICANT |
| Applicant returned to address corrections | 10/23/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 10/29/2020 | PARISA ZAHABI |
| Plan Check Approved | 11/10/2020 | PARISA ZAHABI |
| Issued | 11/11/2020 | APPLICANT |
| CofO in Progress | 6/27/2022 | KENNETH NAGLE |
| Permit Finaled | 6/29/2022 | DANIEL ORRANTE |
| CofO Issued | 6/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/27/2020 | RUBEN VASQUEZ |
| ZI | Cleared | 8/27/2020 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/1/2020 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 10/9/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/13/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 10/29/2020 | PARISA ZAHABI |
| Green Code | Cleared | 11/10/2020 | PARISA ZAHABI |
Contact Information
| Architect | Bambrough,, Patrick; Lic. No.: C34299 | 4132 ALLA ROAD LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/9/2020 | Approved | RICHARD ROBLES |
| Underground Mechanical | 12/9/2020 | Approved | RICHARD ROBLES |
| Footing/Foundation/Slab | 2/25/2021 | Partial Approval | RICHARD ROBLES |
| PLUMBING-Rough | 3/2/2021 | Partial Approval | RICHARD ROBLES |
| Footing/Foundation/Slab | 3/24/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/24/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 5/4/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 7/30/2021 | Corrections Issued | KENNETH NAGLE |
| Special/Order Compliance | 8/4/2021 | Corrections Issued | KENNETH NAGLE |
| Special/Order Compliance | 8/20/2021 | Partial Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 8/31/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/3/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/3/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/17/2021 | Approved | OGANES TARAKHCHYAN |
| Sewer | 9/17/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/27/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/27/2021 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 9/27/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 11/2/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 11/30/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 12/2/2021 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/13/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/17/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/17/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/14/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/14/2022 | Approved | JOHNNY MIRANDA |
| Gas Test | 5/11/2022 | Approved | JOHNNY MIRANDA |
| Final | 5/20/2022 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Final | 5/20/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 5/20/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 5/20/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 6/3/2022 | Approved | KENNETH NAGLE |