6275 W OLYMPIC BLVD 90048

Certificate Information: 6275 W OLYMPIC BLVD 90048

Application / Permit
20014-30000-02748
Plan Check / Job No.
B20WL02788
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Interior remodel and add 20 sf bay window to ground floor of (E) duplex
Permit Issued
Issued on 10/17/2020
Issuing Office
Current Status
CofO Issued on 11/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 JASON JANGADA
Corrections Issued 7/9/2020 JASON JANGADA
Plan Check Approved 10/1/2020 PARISA ZAHABI
Issued 10/17/2020 APPLICANT
Building Plans Picked Up 10/19/2020 APPLICANT
CofO in Progress 10/14/2022 MICHAEL LEWIS
Permit Finaled 11/6/2022 DEROLD HAUFF
CofO Issued 11/6/2022 DEROLD HAUFF
Permit Finaled 11/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/24/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 7/24/2020 HISASHI KOBAYAKAWA
CPC Cleared 7/27/2020 MARITZA PRZEKOP
Eng Process Fee Ord 176,300 Cleared 7/28/2020 HISASHI KOBAYAKAWA
HPOZ Cleared 8/28/2020 JONATHAN KAPLAN
"Q" conditions Cleared 9/2/2020 JONATHAN KAPLAN
ZI Cleared 9/2/2020 JONATHAN KAPLAN
Tenant Habitability Plan Cleared 9/18/2020 PHILLIP MUNGUIA

Contact Information

Contractor M J M Builders Incorporated; Lic. No.: 809159-B 5008 WEST JEFFERSON BLVD      LOS ANGELES, CA 90016
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/9/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 12/15/2020 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 12/15/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 12/15/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 12/15/2020 Approved STUART CHAPMAN
PLUMBING-Rough 12/15/2020 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 12/24/2020 Approved OSVALDO PARAMO
Insulation 12/24/2020 Partial Approval OSVALDO PARAMO
METHANE-Barrier 12/24/2020 Approved OSVALDO PARAMO
METHANE-Subgrade 12/24/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/29/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 12/29/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 1/11/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/11/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 1/12/2021 Partial Approval STUART CHAPMAN
Shower Pan 1/12/2021 Approved STUART CHAPMAN
Final 9/15/2022 Corrections Issued MICHAEL LEWIS
Green Building Final 9/15/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 9/15/2022 Approved MICHAEL LEWIS
Final 10/13/2022 Conditional Approval MICHAEL LEWIS