11640-11642 N MCLENNAN AVE 91344

Certificate Information: 11640-11642 N MCLENNAN AVE 91344

Application / Permit
20014-30000-02706
Plan Check / Job No.
B20WL02744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED (E) 2-CAR GARAGE TO ADU PER GCS 65852.2(e)(1)(A). NO NEW ADDED SF AREA. ALL WORK PER WFPP.
Permit Issued
Issued on 1/22/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 MANUEL GARCIA
Corrections Issued 7/7/2020 MANUEL GARCIA
Applicant returned to address corrections 7/22/2020 PARISA ZAHABI
Plan Check Approved 8/25/2020 RICHARD GARCIA
Building Plans Picked Up 8/26/2020 APPLICANT
Issued 1/22/2021 APPLICANT
CofO in Progress 12/5/2022 JAVIER RAMOS JR
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/7/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 7/7/2020 ADRIAN CASTRO
Sewer availability Cleared 7/7/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/28/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 8/17/2020 KIRK LINKLATER

Contact Information

Contractor A F C O Construction Company Inc; Lic. No.: 837131-B 26012 TRANA CIRCLE      CALABASAS, CA 91302

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/2/2021 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 2/2/2021 Not Ready for Inspection MARK JOHNSON
Gas Test 2/2/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 2/2/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 2/2/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 2/5/2021 Approved MARK JOHNSON
Wood Frame 2/12/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 3/4/2021 Corrections Issued MARK JOHNSON
HVAC-Rough 3/4/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 3/4/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 6/8/2021 Approved MARK JOHNSON
HVAC-Rough 6/8/2021 Approved MARK JOHNSON
PLUMBING-Rough 6/8/2021 Approved MARK JOHNSON
Sewer 6/8/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 6/15/2021 Partial Approval MARK JOHNSON
Wood Frame 6/15/2021 Corrections Issued MARK JOHNSON
Drywall Nailing 6/22/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 6/22/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 6/22/2021 Not Ready for Inspection MARK JOHNSON
Insulation 6/22/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 6/22/2021 Not Ready for Inspection MARK JOHNSON
Wood Frame 6/22/2021 Not Ready for Inspection MARK JOHNSON
Insulation 7/14/2021 Corrections Issued JENNIFER RABUCHIN
Wood Frame 7/14/2021 Partial Approval JENNIFER RABUCHIN
Insulation 7/21/2021 Conditional Approval MARK JOHNSON
Wood Frame 7/21/2021 Approved MARK JOHNSON
Drywall Nailing 8/3/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 9/9/2021 Approved MARK JOHNSON
Green Building Rough 9/9/2021 Approved MARK JOHNSON
Shower Pan 9/9/2021 Approved MARK JOHNSON
Final 7/11/2022 Corrections Issued DEANDRE HOFFMAN
Green Building Final 7/11/2022 Not Ready for Inspection DEANDRE HOFFMAN
Smoke Detectors 7/11/2022 Approved DEANDRE HOFFMAN
Final 7/29/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/29/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 9/7/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/7/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 12/5/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/5/2022 Approved JAVIER RAMOS JR