7615 N TUJUNGA AVE 91605

Certificate Information: 7615 N TUJUNGA AVE 91605

Application / Permit
20014-30000-02649
Plan Check / Job No.
B20WL02690
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) Garage convertion into ADU and addition to ADU.PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/15/2021
Issuing Office
Current Status
CofO Issued on 12/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 JAHANSHAH POURHASSAN
Corrections Issued 7/14/2020 JAHANSHAH POURHASSAN
Building Plans Picked Up 7/24/2020 APPLICANT
Plan Check Approved 1/21/2021 ALFREDO JARA
Issued 2/15/2021 APPLICANT
CofO in Progress 12/6/2023 CHRISTOPHER ROJAS
CofO Issued 12/28/2023 RUBEN SALAS
Permit Finaled 12/28/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/3/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/3/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/3/2020 LEE GUILBEAUX
Sewer availability Cleared 9/3/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 9/25/2020 KURT CORRAL
Flood clearance Cleared 1/8/2021 RAYMOND LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/5/2021 Not Ready for Inspection JOHN HAYES
FLOOD-Elevation Certificate 4/15/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/15/2021 Not Ready for Inspection JOHN HAYES
FLOOD-Elevation Certificate 4/27/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/27/2021 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/19/2021 Corrections Issued DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval MICHEL ABAJAN
Insulation 9/29/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/13/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 10/13/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/19/2022 Approved CHRISTOPHER DELLEFIELD
FLOOD-Proofing Certificate 10/19/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 10/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 10/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/4/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 11/4/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 11/4/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 11/28/2022 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 11/28/2022 Approved MATTHEW NELSON
Insulation 12/2/2022 Approved DONALD CRICHLOW
Drywall Nailing 12/6/2022 Approved DONALD CRICHLOW
Interior/Exterior Lathing 12/6/2022 Approved DONALD CRICHLOW
Shower Pan 12/6/2022 Approved DONALD CRICHLOW
ELECTRICAL-Final 2/13/2023 Corrections Issued MATTHEW NELSON
Gas Test 2/16/2023 Approved WILLIAM WREN
PLUMBING-Final 2/16/2023 Not Ready for Inspection WILLIAM WREN
FLOOD-Elevation Certificate 8/1/2023 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 8/1/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 11/1/2023 Corrections Issued DAVID MATSON
FLOOD-Elevation Certificate 11/1/2023 Approved DAVID MATSON
Final 11/1/2023 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 11/1/2023 Approved DAVID MATSON
Green Building Final 11/1/2023 Approved DAVID MATSON
HVAC-Final 11/1/2023 Approved DAVID MATSON
PLUMBING-Final 11/1/2023 Corrections Issued DAVID MATSON
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Approved DAVID MATSON
Service/Power Release 11/1/2023 Not Ready for Inspection DAVID MATSON
Smoke Detectors 11/1/2023 Corrections Issued DAVID MATSON
Final 11/6/2023 Partial Approval CHRISTOPHER ROJAS
Smoke Detectors 11/6/2023 Approved CHRISTOPHER ROJAS
Final 12/6/2023 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 12/6/2023 Approved CHRISTOPHER ROJAS