9477 W LLOYDCREST DR 90210
Certificate Information: 9477 W LLOYDCREST DR 90210
- Application / Permit
- 20014-30000-02611
- Plan Check / Job No.
- B20WL02655
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND FLOOR ADDITION TO EXISTING 2-STORY SFD WITH ATTACHED GARAGE AND VOVERED PATIO AT THE REAR
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | TARIK SAOUD |
| Corrections Issued | 7/19/2020 | TARIK SAOUD |
| Quality Review Completed | 7/22/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/15/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 3/3/2021 | TARIK SAOUD |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Plan Check Approved | 3/19/2021 | TARIK SAOUD |
| Issued | 10/19/2021 | APPLICANT |
| CofO in Progress | 6/7/2024 | RAUL BARAJAS |
| CofO Issued | 6/10/2024 | RONALD MYRICK |
| Permit Finaled | 6/10/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 7/24/2020 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 7/28/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/28/2020 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/31/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 11/16/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | RAYMOND MUGAMBWA |
| ZA Case | Cleared | 2/19/2021 | LOUIS ORTEGA |
| Excavation more than 5-ft deep | Cleared | 3/19/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 3/19/2021 | TARIK SAOUD |
Contact Information
| Contractor | Tm Design Build; Lic. No.: 1068098-B | 27475 YNEZ RD #349 TEMECULA, CA 92591 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
| Engineer | Su,, Yu-Ting; Lic. No.: C76714 | 28 SAGE LAKE FOREST, CA 92630 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2022 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/9/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/11/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 6/21/2022 | Conditional Approval | ADAM ESCOTO |
| Footing/Foundation/Slab | 6/22/2022 | Approved | RAUL BARAJAS |
| Deputy Steel/Welding | 6/28/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 6/29/2022 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 9/7/2022 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Approved | RAUL BARAJAS |
| Masonry Wall/Backfill | 9/27/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/16/2022 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 12/21/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/22/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 12/22/2022 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 1/4/2023 | Conditional Approval | RAUL BARAJAS |
| Insulation | 1/5/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/17/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/17/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/25/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/25/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/3/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 5/2/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/25/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 5/25/2023 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/18/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 8/18/2023 | Approved | RAUL BARAJAS |
| Final | 12/14/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 12/14/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/14/2023 | Approved | RAUL BARAJAS |
| Final | 6/6/2024 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 6/6/2024 | Approved | RAUL BARAJAS |