2137 S GLYNDON AVE 90291
Certificate Information: 2137 S GLYNDON AVE 90291
- Application / Permit
- 20014-30000-02575
- Plan Check / Job No.
- B20WL02609
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel for 2-story SFR.
- Permit Issued
- Issued on 1/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/20/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 7/23/2020 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/16/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/30/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/17/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/5/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 1/19/2021 | APPLICANT |
| Building Plans Picked Up | 1/20/2021 | APPLICANT |
| CofO in Progress | 12/30/2021 | DAVID FEILER |
| Permit Finaled | 1/4/2022 | DANIEL ORRANTE |
| CofO Issued | 1/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/12/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/12/2020 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 11/17/2020 | SARAH YOUSSEF |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Zepeda General Building; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/22/2021 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/29/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/2/2021 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/3/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 4/19/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 4/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 4/30/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/5/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/5/2021 | Approved | JOHNNY MIRANDA |
| Wood Frame | 5/5/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/13/2021 | Approved | PIERRE VEGA |
| Green Building Rough | 5/13/2021 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 5/13/2021 | Not Ready for Inspection | PIERRE VEGA |
| Wood Frame | 5/13/2021 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 5/14/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 5/19/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/2/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 6/10/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/21/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/17/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 11/17/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 11/22/2021 | Approved | DAVID FEILER |
| PLUMBING-Final | 11/22/2021 | Approved | DAVID FEILER |
| Service/Power Release | 11/22/2021 | Approved | DAVID FEILER |
| Final | 12/8/2021 | Corrections Issued | DAVID FEILER |
| Green Building Final | 12/8/2021 | Approved | DAVID FEILER |
| HVAC-Final | 12/8/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 12/8/2021 | Approved | DAVID FEILER |
| Final | 12/30/2021 | OK to Issue CofO | DAVID FEILER |
| HVAC-Final | 12/30/2021 | Approved | DAVID FEILER |