3004 N GREENTREE CT 90077

Certificate Information: 3004 N GREENTREE CT 90077

Application / Permit
20014-30000-02535
Plan Check / Job No.
B20WL02566
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior & exterior remodel to (E) 2 story SFD. Reconfigure & expand existing staircase.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 7/22/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 7/29/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/7/2021 APPLICANT
Plan Check Approved 3/31/2021 VLADIMIR ARUTYUNYAN
Issued 4/28/2021 APPLICANT
CofO in Progress 8/11/2023 CHRISTOPHER WILSON
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/9/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/15/2020 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 1/14/2021 BRIAN MILLER
Specific Plan Cleared 3/1/2021 LAURA FRAZIN-STEELE
Specific Plan Cleared 3/1/2021 LAURA FRAZIN-STEELE

Contact Information

Contractor B H C; Lic. No.: 960037-B 4607 LAKEVIEW CANYON RD #595      WESTLAKE VILLAGE, CA 91361
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2021 Approved ANTHONY MCDOWALL
PLUMBING-Rough 6/3/2021 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 7/12/2021 Corrections Issued ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 7/12/2021 Corrections Issued ANTHONY MCDOWALL
ELECTRICAL-Rough 7/15/2021 Approved ANTHONY MCDOWALL
HVAC-Rough 7/15/2021 Approved ANTHONY MCDOWALL
PLUMBING-Rough 7/15/2021 Approved ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Approved ANTHONY MCDOWALL
Deputy Wood Construction 7/20/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 8/12/2021 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 9/30/2021 Approved JAVIER RAMOS JR
Insulation 10/5/2021 Approved STEPHANIE SWANSON
Drywall Nailing 10/18/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 10/20/2021 Approved CARLOS MATAMOROS
Shower Pan 11/2/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 11/23/2021 Partial Approval RYAN SALAZAR
Gas Test 5/23/2022 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 4/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 4/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 4/24/2023 Corrections Issued MICHAEL PELHAM
Final 4/24/2023 Corrections Issued MICHAEL PELHAM
PLUMBING-Final 4/24/2023 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Final 5/25/2023 Approved STEPHANIE SWANSON
HVAC-Final 5/25/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 5/25/2023 Approved STEPHANIE SWANSON
Final 6/14/2023 Corrections Issued BRENDAN LOONEY
HVAC-Final 6/14/2023 Approved BRENDAN LOONEY
Final 8/10/2023 OK to Issue CofO CHRISTOPHER WILSON
Wood Frame 8/10/2023 Approved CHRISTOPHER WILSON