16577 W VIA FLORESTA 90272

Certificate Information: 16577 W VIA FLORESTA 90272

Application / Permit
20014-30000-02532
Plan Check / Job No.
B20WL02565
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel bathroom, kitchen, and laundry room. Enclose 2nd floor deck. Per engineering design.
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2020 APPLICANT
Assigned to Plan Check Engineer 6/24/2020 JASON JANGADA
Corrections Issued 6/25/2020 JASON JANGADA
Building Plans Picked Up 6/26/2020 APPLICANT
Applicant returned to address corrections 3/24/2021 JASON JANGADA
Applicant returned to address corrections 5/3/2021 FELIPE HERNANDEZ
Plan Check Approved 5/21/2021 ALFREDO JARA
Issued 6/9/2021 APPLICANT
CofO in Progress 5/6/2022 ANDREW NAVE
Permit Finaled 5/16/2022 DANIEL ORRANTE
CofO Issued 5/16/2022 DANIEL ORRANTE
Permit Finaled 5/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/27/2020 BARTON HOLMES
ZA Case Cleared 10/27/2020 NOAH MCCOY
ZA Case Cleared 10/27/2020 NOAH MCCOY
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
BHO/Hillside ordinance Cleared 1/5/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 1/26/2021 TRACY TATE
BHO/Hillside ordinance Cleared 1/26/2021 TRACY TATE
BHO/Hillside ordinance Cleared 1/26/2021 TRACY TATE
BHO/Hillside ordinance Cleared 1/26/2021 TRACY TATE
Roof/Waste drainage to street Cleared 1/26/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 4/5/2021 TRACY TATE
Coastal Zone Cleared 4/26/2021 RICHARD REASER

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor H A S Construction Inc; Lic. No.: 538538-B 11272 WASHINGTON PL      CULVER CITY, CA 90230

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/10/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Partial Approval ANDREW NAVE
HVAC-Rough 6/10/2021 Approved ANDREW NAVE
PLUMBING-Rough 6/10/2021 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 6/16/2021 Conditional Approval ANDREW NAVE
Drywall Nailing 6/17/2021 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 6/17/2021 Approved ANDREW NAVE
Footing/Foundation/Slab 6/17/2021 Approved ANDREW NAVE
Insulation 6/17/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 7/14/2021 Partial Approval ANDREW NAVE
Gas Test 7/14/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 7/14/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Approved MORRIS JACKSON
Insulation 7/20/2021 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 7/27/2021 Conditional Approval ANDREW NAVE
BUILDING-Rough-Frame 7/28/2021 Partial Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Approved ANDREW NAVE
Insulation 7/30/2021 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 8/2/2021 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 8/5/2021 Partial Inspection ANDREW NAVE
ELECTRICAL-Rough 8/5/2021 Approved ANDREW NAVE
Green Building Rough 8/5/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 8/5/2021 Approved ANDREW NAVE
PLUMBING-Rough 8/5/2021 Approved ANDREW NAVE
Insulation 8/11/2021 Approved MORRIS JACKSON
Shower Pan 8/11/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/12/2021 Partial Approval MORRIS JACKSON
Pre-Inspection 8/12/2021 Partial Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 8/16/2021 Approved JESUS RODRIGUEZ
Drywall Nailing 8/16/2021 Approved JESUS RODRIGUEZ
Green Building Rough 8/16/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/16/2021 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/28/2022 Approved ANDREW NAVE
Final 4/28/2022 Corrections Issued ANDREW NAVE
Green Building Final 4/28/2022 Corrections Issued ANDREW NAVE
HVAC-Final 4/28/2022 Approved ANDREW NAVE
PLUMBING-Final 4/28/2022 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 4/28/2022 Corrections Issued ANDREW NAVE
Final 5/6/2022 OK to Issue CofO ANDREW NAVE
Green Building Final 5/6/2022 Approved ANDREW NAVE
Smoke Detectors 5/6/2022 Approved ANDREW NAVE