134 S MARTEL AVE 90036
Certificate Information: 134 S MARTEL AVE 90036
- Application / Permit
- 20014-30000-02504
- Plan Check / Job No.
- B20WL02542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE ADDITION AND CONVERSION TO ADU
- Permit Issued
- Issued on 1/22/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 7/30/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 8/7/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 9/30/2020 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 1/21/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 1/22/2021 | APPLICANT |
| Building Plans Picked Up | 1/25/2021 | APPLICANT |
| CofO in Progress | 10/11/2022 | MICHAEL LEWIS |
| Permit Finaled | 10/15/2022 | DEROLD HAUFF |
| CofO Issued | 10/15/2022 | DEROLD HAUFF |
| Permit Finaled | 10/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 9/21/2020 | DANIEL MATA |
| Low Impact Development | Cleared | 12/21/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 12/30/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 12/30/2020 | ELAINE LEI |
| Sewer availability | Cleared | 12/30/2020 | ELAINE LEI |
Contact Information
| Contractor | Guerra Brian Construction Inc; Lic. No.: 913001-B | 31502 HIPSHOT DRIVE CASTAIC, CA 91384 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 3/8/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 3/8/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/31/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/9/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/9/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/9/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/8/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/8/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/8/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/8/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Rough | 7/8/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/16/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/21/2021 | Approved | CHRIS CHRISTENSEN |
| Sewer | 11/9/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/15/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 2/15/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/15/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/2/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 3/2/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/2/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 5/3/2022 | Corrections Issued | ADAM ESCOTO |
| Green Building Final | 5/3/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Approved | ADAM ESCOTO |
| Smoke Detectors | 5/3/2022 | Approved | ADAM ESCOTO |
| Final | 8/4/2022 | Corrections Issued | MICHAEL LEWIS |
| Final | 8/22/2022 | OK to Issue CofO | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/7/2022 | Approved | MICHAEL LEWIS |
| Service/Power Release | 9/7/2022 | Approved | MICHAEL LEWIS |