Permit Issued
Issued on 1/22/2021
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 7/30/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/7/2020 TARIK SAOUD
Applicant returned to address corrections 9/30/2020 VLADIMIR ARUTYUNYAN
Plan Check Approved 1/21/2021 VLADIMIR ARUTYUNYAN
Issued 1/22/2021 APPLICANT
Building Plans Picked Up 1/25/2021 APPLICANT
CofO in Progress 10/11/2022 MICHAEL LEWIS
Permit Finaled 10/15/2022 DEROLD HAUFF
CofO Issued 10/15/2022 DEROLD HAUFF
Permit Finaled 10/15/2022 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 9/21/2020 DANIEL MATA
Low Impact Development Cleared 12/21/2020 SARAH YOUSSEF
Address approval Cleared 12/30/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 12/30/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 12/30/2020 ELAINE LEI
Sewer availability Cleared 12/30/2020 ELAINE LEI

Contact Information

Contractor Guerra Brian Construction Inc; Lic. No.: 913001-B 31502 HIPSHOT DRIVE      CASTAIC, CA 91384

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 3/8/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 3/8/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/31/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/31/2021 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/9/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/9/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/9/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/9/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/8/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 7/8/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/8/2021 Approved CHRIS CHRISTENSEN
Insulation 7/8/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/8/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Rough 7/8/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/16/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 7/21/2021 Approved CHRIS CHRISTENSEN
Sewer 11/9/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 2/15/2022 Corrections Issued CHRIS CHRISTENSEN
Gas Test 2/15/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 2/15/2022 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Final 3/2/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 3/2/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/2/2022 Approved CHRIS CHRISTENSEN
Final 5/3/2022 Corrections Issued ADAM ESCOTO
Green Building Final 5/3/2022 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Approved ADAM ESCOTO
Smoke Detectors 5/3/2022 Approved ADAM ESCOTO
Final 8/4/2022 Corrections Issued MICHAEL LEWIS
Final 8/22/2022 OK to Issue CofO MICHAEL LEWIS
ELECTRICAL-Final 9/7/2022 Approved MICHAEL LEWIS
Service/Power Release 9/7/2022 Approved MICHAEL LEWIS