14025 W HESBY ST 91423
Certificate Information: 14025 W HESBY ST 91423
- Application / Permit
- 20014-30000-02498
- Plan Check / Job No.
- B20WL02533
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREQULAR SHAPE ADDITION OF 1073 SF TO THE (E) SFD, 60 SF FRONT COVERED PATIO W/ ADDING 326 SF ATTACHED GARAGE TO THE FRONT YARD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 4/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2020 | PARISA ZAHABI |
| Corrections Issued | 7/11/2020 | PARISA ZAHABI |
| Quality Review Completed | 7/16/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/12/2020 | PARISA ZAHABI |
| Plan Check Approved | 8/13/2020 | PARISA ZAHABI |
| Issued | 8/19/2020 | APPLICANT |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| CofO in Progress | 4/8/2021 | CHARLES POWELL |
| Permit Finaled | 4/16/2021 | DANIEL ORRANTE |
| CofO Issued | 4/16/2021 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 7/22/2020 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 7/30/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/4/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/4/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | S R S Builders Inc; Lic. No.: 972622-B | 9045 ETON AVENUE UNIT D CANOGA PARK, CA 91304 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 9/10/2020 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/28/2020 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 9/28/2020 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 10/8/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/19/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/22/2020 | Partial Approval | CHARLES POWELL |
| HVAC-Rough | 10/28/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 10/28/2020 | Approved | CHARLES POWELL |
| Deputy Wood Construction | 10/30/2020 | Conditional Approval | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 11/5/2020 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | BEAU COLLINS |
| Shower Pan | 11/5/2020 | Approved | BEAU COLLINS |
| Wood Frame | 11/5/2020 | Not Ready for Inspection | BEAU COLLINS |
| ELECTRICAL-Rough | 11/10/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/16/2020 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/23/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 11/23/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/8/2020 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 12/8/2020 | Approved | ARAM AVEDISIAN |
| Insulation | 12/14/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 12/21/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 12/21/2020 | Approved | MATTHEW NELSON |
| Gas Test | 3/5/2021 | Approved | CHARLES POWELL |
| Service/Power Release | 3/5/2021 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Final | 3/16/2021 | Approved | CHARLES POWELL |
| PLUMBING-Final | 3/16/2021 | Approved | CHARLES POWELL |
| HVAC-Final | 3/17/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | DANIEL DREW |
| Final | 3/26/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 3/26/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Approved | DANIEL DREW |
| Service/Power Release | 3/26/2021 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 3/26/2021 | Approved | DANIEL DREW |
| Final | 4/7/2021 | OK to Issue CofO | CHARLES POWELL |
| Service/Power Release | 4/7/2021 | Approved | CHARLES POWELL |