17841-17843 W TARZANA ST 91316

Certificate Information: 17841-17843 W TARZANA ST 91316

Application / Permit
20014-30000-02477
Plan Check / Job No.
B20WL02519
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Attached garage conversion & 2nd story ADU addition to (E) 2 story SFD.
Permit Issued
Issued on 10/29/2021
Issuing Office
Valley
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 7/22/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 7/28/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 8/6/2020 APPLICANT
Applicant returned to address corrections 3/4/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 10/15/2021 VLADIMIR ARUTYUNYAN
Issued 10/29/2021 APPLICANT
CofO in Progress 10/4/2022 TROY SANDERS
CofO Issued 2/4/2023 MICHAEL SMITH
Permit Finaled 2/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Permit Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 9/8/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 9/14/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 9/21/2021 ALEXANDER ANDREWS
GPI Written Notices Cleared 10/15/2021 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 5649 VANTAGE AVE      VALLEY VILLAGE, CA 91607

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 12/21/2021 Approved DAVID SANDOVAL
Sewer 12/21/2021 Approved DAVID SANDOVAL
Underground Mechanical 12/21/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 2/7/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 2/7/2022 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Approved DAVID SANDOVAL
Drywall Nailing 3/16/2022 Partial Approval DAVID SANDOVAL
Underground Mechanical 3/16/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 4/6/2022 Not Ready for Inspection DAVID SANDOVAL
Gas Test 4/6/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 4/6/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/6/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/6/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 4/12/2022 Not Ready for Inspection SEAN WIRCH
Gas Test 4/12/2022 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 4/12/2022 Not Ready for Inspection SEAN WIRCH
Interior/Exterior Lathing 4/12/2022 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 4/12/2022 Not Ready for Inspection SEAN WIRCH
ELECTRICAL-Rough 4/19/2022 Approved DAVID SANDOVAL
Gas Test 4/19/2022 Partial Inspection DAVID SANDOVAL
HVAC-Rough 4/19/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/19/2022 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 4/19/2022 Approved DAVID SANDOVAL
Insulation 4/22/2022 Corrections Issued DAVID SANDOVAL
Drywall Nailing 5/3/2022 Approved DAVID SANDOVAL
Green Building Rough 5/3/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 5/3/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 8/22/2022 Approved DAVID SANDOVAL
Final 8/22/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 8/22/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 8/22/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Not Ready SEAN HAUPT
ELECTRICAL-Final 10/3/2022 Approved TROY SANDERS
Final 10/3/2022 OK to Issue CofO TROY SANDERS
Green Building Final 10/3/2022 Approved TROY SANDERS
Pre-Inspection 10/3/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 10/3/2022 Approved TROY SANDERS