8216 S TUSCANY AVE 90293
Certificate Information: 8216 S TUSCANY AVE 90293
- Application / Permit
- 20014-30000-02445
- Plan Check / Job No.
- B20WL02461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO EXISNTING 1-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. COMPLY WITH DEPARTMENT ORDER effective date 11/06/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 881593.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Current Status
- CofO Issued on 6/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2020 | SERGIO SILVA |
| Corrections Issued | 7/17/2020 | SERGIO SILVA |
| Quality Review Completed | 7/23/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/24/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 9/28/2020 | SERGIO SILVA |
| Plan Check Approved | 11/16/2020 | SERGIO SILVA |
| Issued | 11/19/2020 | APPLICANT |
| Building Plans Picked Up | 12/1/2020 | APPLICANT |
| CofO in Progress | 6/1/2022 | MARIAN PODPORA |
| Permit Finaled | 6/30/2022 | BRUCE TODD |
| CofO Issued | 6/30/2022 | BRUCE TODD |
| Permit Finaled | 6/30/2022 | BRUCE TODD |
Permit Application Clearance Information
| Permit | Cleared | 8/14/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | TRACY TATE |
| Hydrant and Access approval | Cleared | 9/18/2020 | KURT CORRAL |
| GPI Written Notices | Cleared | 9/28/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 9/28/2020 | SERGIO SILVA |
| Green Code | Cleared | 9/28/2020 | SERGIO SILVA |
| Low Impact Development | Cleared | 10/22/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/16/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/16/2020 | DINAH GARIN |
Contact Information
| Contractor | Seitz M J Construction; Lic. No.: 801839-B | 531 MAIN STREET #977 EL SEGUNDO, CA 90245 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2021 | Approved | MARIAN PODPORA |
| METHANE-Barrier | 2/10/2021 | Approved | MARIAN PODPORA |
| METHANE-Subgrade | 2/10/2021 | Approved | MARIAN PODPORA |
| BUILDING-Rough-Frame | 2/24/2021 | Partial Approval | MARIAN PODPORA |
| Green Building Rough | 2/24/2021 | Not Ready for Inspection | MARIAN PODPORA |
| METHANE-Rough | 2/24/2021 | Approved | MARIAN PODPORA |
| Deputy Methane Barrier | 3/8/2021 | Approved | MARIAN PODPORA |
| PLUMBING-Rough | 3/19/2021 | Not Ready for Inspection | RYAN BARNES |
| Underground Mechanical | 3/19/2021 | Approved | RYAN BARNES |
| PLUMBING-Rough | 4/13/2021 | Approved | MARIAN PODPORA |
| Underground Mechanical | 4/13/2021 | Partial Approval | MARIAN PODPORA |
| Structural Steel Frame | 4/27/2021 | Approved | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 6/4/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Green Building Rough | 6/4/2021 | Partial Inspection | MARIAN PODPORA |
| Rough-Elec/Plmb/HVAC | 6/4/2021 | Partial Approval | MARIAN PODPORA |
| ELECTRICAL-Rough | 6/7/2021 | Approved | MARIAN PODPORA |
| HVAC-Rough | 6/7/2021 | Partial Approval | MARIAN PODPORA |
| BUILDING-Rough-Frame | 6/23/2021 | Approved | MARIAN PODPORA |
| Green Building Rough | 6/23/2021 | Approved | MARIAN PODPORA |
| HVAC-Rough | 6/23/2021 | Approved | MARIAN PODPORA |
| Interior/Exterior Lathing | 6/23/2021 | Partial Approval | MARIAN PODPORA |
| Insulation | 7/1/2021 | Approved | MARIAN PODPORA |
| Drywall Nailing | 7/15/2021 | Partial Approval | MARIAN PODPORA |
| Service/Power Release | 7/29/2021 | Approved | JOHN MATTILLO |
| Shower Pan | 8/24/2021 | Approved | MARIAN PODPORA |
| Interior/Exterior Lathing | 8/31/2021 | Partial Approval | MARIAN PODPORA |
| ELECTRICAL-Final | 12/9/2021 | Corrections Issued | MARIAN PODPORA |
| Gas Test | 12/9/2021 | Approved | MARIAN PODPORA |
| HVAC-Final | 12/9/2021 | Corrections Issued | MARIAN PODPORA |
| PLUMBING-Final | 12/9/2021 | Corrections Issued | MARIAN PODPORA |
| ELECTRICAL-Final | 12/13/2021 | Approved | MARIAN PODPORA |
| HVAC-Final | 12/13/2021 | Approved | MARIAN PODPORA |
| PLUMBING-Final | 12/13/2021 | Approved | MARIAN PODPORA |
| Drywall Nailing | 4/15/2022 | Approved | JOHN MATTILLO |
| Final | 4/15/2022 | Conditional Approval | JOHN MATTILLO |
| Green Building Final | 4/15/2022 | Approved | JOHN MATTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | JOHN MATTILLO |
| Smoke Detectors | 4/15/2022 | Approved | JOHN MATTILLO |