2014 S FAIRBURN AVE 90025
Certificate Information: 2014 S FAIRBURN AVE 90025
- Application / Permit
- 20014-30000-02421
- Plan Check / Job No.
- B20WL02426
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ground floor addition to create 3-story SFD with an attached garage.
- Permit Issued
- Issued on 1/21/2022
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2020 | TARIK SAOUD |
| Corrections Issued | 7/8/2020 | TARIK SAOUD |
| Quality Review Completed | 7/14/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/28/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 2/19/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/25/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/27/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 8/9/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/26/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 8/31/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 9/22/2021 | TARIK SAOUD |
| Plan Check Approved | 1/5/2022 | TARIK SAOUD |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Issued | 1/21/2022 | APPLICANT |
| CofO in Progress | 3/16/2023 | ROBERT CHAVEZ |
| Permit Finaled | 4/6/2023 | DANIEL SANCHEZ |
| CofO Issued | 4/6/2023 | DANIEL SANCHEZ |
| Permit Finaled | 4/6/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2020 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/5/2020 | OSCAR GUTIERREZ |
| Sewer availability | Cleared | 8/5/2020 | OSCAR GUTIERREZ |
| Hydrant and Access approval | Cleared | 8/7/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/28/2020 | ROBIN YAMADA |
| Grading Pre-Inspection | Cleared | 12/28/2020 | TARIK SAOUD |
| Frnt yard landscape/Water mgmt | Cleared | 3/18/2021 | RUBEN VASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2022 | Approved | JOHN TCHANG |
| METHANE-Subgrade | 2/15/2022 | Approved | JOHN TCHANG |
| Deputy Drilled-In Anchors | 2/22/2022 | Approved | PATRICK QUALEY |
| METHANE-Barrier | 2/22/2022 | Approved | PATRICK QUALEY |
| Footing/Foundation/Slab | 3/1/2022 | Approved | JOHN TCHANG |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Corrections Issued | JOHN TCHANG |
| Deputy Methane Barrier | 5/11/2022 | Approved | JOHN TCHANG |
| Deputy Wood Construction | 5/13/2022 | Conditional Approval | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 6/7/2022 | Corrections Issued | JOHN TCHANG |
| HVAC-Rough | 6/7/2022 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 6/14/2022 | Not Ready for Inspection | JOHN TCHANG |
| Green Building Rough | 6/14/2022 | Approved | JOHN TCHANG |
| METHANE-Rough | 6/14/2022 | Approved | JOHN TCHANG |
| PLUMBING-Rough | 6/14/2022 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 6/16/2022 | Corrections Issued | JOHN TCHANG |
| Interior/Exterior Lathing | 6/23/2022 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | JOHN TCHANG |
| Shower Pan | 6/28/2022 | Approved | JOHN TCHANG |
| Insulation | 7/7/2022 | Not Ready for Inspection | JOHN TCHANG |
| Insulation | 7/12/2022 | Approved | JOHN TCHANG |
| Drywall Nailing | 7/19/2022 | Approved | JOHN TCHANG |
| Interior/Exterior Lathing | 7/19/2022 | Approved | JOHN TCHANG |
| Gas Test | 9/28/2022 | Approved | JOHN TCHANG |
| PLUMBING-Rough | 10/6/2022 | Approved | HAGOP BADOSSIAN |
| ELECTRICAL-Final | 12/15/2022 | Corrections Issued | JOHN TCHANG |
| HVAC-Final | 12/15/2022 | Approved | JOHN TCHANG |
| PLUMBING-Final | 12/15/2022 | Approved | JOHN TCHANG |
| ELECTRICAL-Final | 1/19/2023 | Approved | JOHN TCHANG |
| PLUMBING-Final | 1/19/2023 | Approved | JOHN TCHANG |
| Service/Power Release | 1/25/2023 | Approved | JOHN TCHANG |
| Final | 2/9/2023 | Conditional Approval | JOHN TCHANG |
| Green Building Final | 2/9/2023 | Approved | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 2/9/2023 | Approved | JOHN TCHANG |