3507 S SYCAMORE AVE 90016

Certificate Information: 3507 S SYCAMORE AVE 90016

Application / Permit
20014-30000-02410
Plan Check / Job No.
B20WL02411
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) S.F.R & ADDITION OF (N) MASTER SUITE & LAUNDRY AREA
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 2/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 MARJAN SHENASI
Corrections Issued 6/15/2020 MARJAN SHENASI
Applicant returned to address corrections 8/26/2020 JASON JANGADA
Applicant returned to address corrections 9/17/2020 JASON JANGADA
Plan Check Approved 9/24/2020 JASON JANGADA
Issued 10/9/2020 APPLICANT
Building Plans Picked Up 10/13/2020 APPLICANT
CofO in Progress 2/8/2022 JOSE AVILA
Permit Finaled 2/16/2022 DEROLD HAUFF
CofO Issued 2/16/2022 DEROLD HAUFF
Permit Finaled 2/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2020 JAMES KHO
Roof/Waste drainage to street Cleared 8/19/2020 JAMES KHO

Contact Information

Contractor Rank-1 Construction Co; Lic. No.: 960933-B 1698 BRIDGEPORT AVENUE      CLAREMONT, CA 91711
Engineer Gonzalez,, Fernando Francisco; Lic. No.: C53256 11607 AMESTOY AVE      GRANADA HILLS, CA 91344

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/18/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Partial Approval DAVID CHAN
Wood Frame 12/2/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Partial Approval DAVID CHAN
ELECTRICAL-Rough 3/23/2021 Corrections Issued RUBEN SALAS
PLUMBING-Rough 3/23/2021 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 4/7/2021 Approved STUART CHAPMAN
PLUMBING-Rough 4/7/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/26/2021 Partial Inspection SCOTT FINNILA
HVAC-Rough 5/26/2021 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 5/26/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 6/9/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/9/2021 Partial Approval STUART CHAPMAN
Insulation 6/17/2021 Approved STUART CHAPMAN
Drywall Nailing 7/8/2021 Approved STUART CHAPMAN
Gas Test 11/17/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 11/23/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 11/23/2021 Approved STUART CHAPMAN
Final 11/23/2021 Corrections Issued STUART CHAPMAN
Green Building Final 11/23/2021 Approved STUART CHAPMAN
Green Building Rough 11/23/2021 Approved STUART CHAPMAN
HVAC-Final 11/23/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Final 11/23/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 11/23/2021 Approved STUART CHAPMAN
Final 2/3/2022 OK to Issue CofO JOSE AVILA