17401 W SUNBURST ST 91325

Certificate Information: 17401 W SUNBURST ST 91325

Application / Permit
20014-30000-02408
Plan Check / Job No.
B20WL02410
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO AN (E) ONE STORY SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 8/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 TARIK SAOUD
Corrections Issued 7/6/2020 TARIK SAOUD
Quality Review Completed 7/8/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 7/23/2020 TARIK SAOUD
Building Plans Picked Up 7/23/2020 APPLICANT
Issued 8/5/2020 APPLICANT
CofO in Progress 3/16/2021 MARK JOHNSON
CofO Issued 5/1/2021 MICHAEL SMITH
Permit Finaled 5/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/14/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 7/14/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Lau,, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/7/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 8/27/2020 Approved DANIEL ORRANTE
Deputy Drilled-In Anchors 8/28/2020 Conditional Approval MICHAEL TEMPLE
Deputy Reinf. Concrete 9/3/2020 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 9/3/2020 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 9/5/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 10/13/2020 Partial Approval MARK JOHNSON
Green Building Rough 10/13/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 10/19/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 10/19/2020 Approved MARK JOHNSON
Green Building Rough 10/19/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 10/19/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 10/19/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 10/27/2020 Partial Approval MARK JOHNSON
Green Building Rough 10/27/2020 Partial Approval MARK JOHNSON
HVAC-Rough 10/27/2020 Approved MARK JOHNSON
Green Building Rough 10/31/2020 Not Ready for Inspection RAUL BARAJAS
Insulation 10/31/2020 Conditional Approval RAUL BARAJAS
Drywall Nailing 11/4/2020 Approved MARK JOHNSON
Shower Pan 11/4/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 11/9/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 3/15/2021 Approved MARK JOHNSON
ELECTRICAL-Final 3/15/2021 Approved MARK JOHNSON
Final 3/15/2021 OK to Issue CofO MARK JOHNSON
Green Building Final 3/15/2021 Approved MARK JOHNSON
Green Building Rough 3/15/2021 Approved MARK JOHNSON
HVAC-Final 3/15/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 3/15/2021 Approved MARK JOHNSON