2304 S RIDGELEY DR 1-10 90016

Certificate Information: 2304 S RIDGELEY DR 1-10 90016

Application / Permit
20014-30000-02405
Plan Check / Job No.
B20WL02405
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ADDITION TO EXISTING 1 STORY SINGLE FAMILY DWELLING IN THE FRONT OF THE LOT AND AN EXISTING DUPLEX AT THE REAR OF THE LOT TO CREATE A 9-UNIT APARTMENT WITH ATTACHED GARAGE AND AN ATTACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 7/19/2022
Issuing Office
Current Status
CofO Issued on 7/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 VU NGUYEN
Corrections Issued 7/9/2020 VU NGUYEN
Quality Review Completed 7/13/2020 RODOLFO ARIAS
Disabled Access Plans Picked Up 7/27/2020 APPLICANT
Building Plans Picked Up 7/29/2020 APPLICANT
Applicant returned to address corrections 9/1/2020 VU NGUYEN
Applicant returned to address corrections 10/8/2020 VU NGUYEN
Applicant returned to address corrections 8/3/2021 RICHARD GARCIA
Green Plans Picked Up 8/5/2021 APPLICANT
Applicant returned to address corrections 6/22/2022 VU NGUYEN
Plan Check Approved 6/30/2022 VU NGUYEN
Issued 7/19/2022 APPLICANT
CofO Issued 7/23/2025 ERNESTO CORRAL
Permit Finaled 7/23/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/18/2021 JUAN ASHTON
Permit Cleared 4/8/2021 JUAN ASHTON
Low Impact Development Cleared 7/30/2021 ANDRES COVARRUBIAS
Address approval Cleared 8/12/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 8/12/2021 CELINA MORENO
Green Code Cleared 9/2/2021 RICHARD GARCIA
Trees in Parkway Cleared 9/2/2021 JOHN KIM
Sewer availability Cleared 9/8/2021 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 10/12/2021 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 10/12/2021 MAXFIELD VERMY
Density Bonus 12.22.A.25 Cleared 11/30/2021 JAMES MCCARTHY
Hydrant and Access approval Cleared 1/24/2022 MATTHEW CRAIG
Building over 36-ft Cleared 1/31/2022 CALOSHA APPROVED
DAS Clearance Cleared 6/15/2022 VU NGUYEN

Contact Information

Contractor Helio Group; Lic. No.: 1004478-B 8721 SANTA MONICA BLVD STE 224      LOS ANGELES, CA 90069
Engineer , ; Lic. No.: S3340 10561 TAMMY ST      CYPRESS, CA 90630
Engineer Jahani,, Fereidoun; Lic. No.: C62875 3720 BLANCHE ST      PASADENA, CA 91107

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2023 Partial Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 6/20/2023 Approved MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 8/17/2023 Partial Approval MARTIN TAVITIAN
Pre-Inspection 8/30/2023 Approved ALFREDO LOPEZ
Structural Steel Frame 8/30/2023 Partial Approval ALFREDO LOPEZ
Deputy Steel/Welding 9/1/2023 Partial Approval JEROME BLACKWOOD
Green Building Rough 9/8/2023 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 9/8/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Rough 9/14/2023 Partial Approval MARTIN TAVITIAN
Structural Steel Frame 9/14/2023 Partial Approval MARTIN TAVITIAN
Wood Frame 9/14/2023 Partial Approval MARTIN TAVITIAN
Green Building Rough 10/11/2023 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 10/11/2023 Not Ready for Inspection JEROME BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Not Ready for Inspection RICARDO ROBLES
Deputy Drilled-In Anchors 2/14/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/14/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Partial Approval RICARDO ROBLES
Green Building Rough 2/15/2024 Partial Approval RICARDO ROBLES
Wood Frame 2/15/2024 Partial Approval RICARDO ROBLES
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Partial Inspection MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 4/5/2024 Not Ready for Inspection JACOB MYERS
Structural Steel Frame 4/5/2024 Partial Approval JACOB MYERS
Green Building Rough 8/9/2024 Approved DARRYL ARNOLD
Structural Steel Frame 8/9/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 8/9/2024 Conditional Approval DARRYL ARNOLD
Insulation 8/20/2024 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 8/21/2024 Not Ready for Inspection MARTIN TAVITIAN
Pre-Inspection 8/22/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 9/5/2024 Partial Approval MARTIN TAVITIAN
Insulation 9/5/2024 Approved MARTIN TAVITIAN
Interior/Exterior Lathing 9/5/2024 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 11/4/2024 Partial Approval CHRISTOPHER BLACKWOOD
Special/Order Compliance 1/27/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Special/Order Compliance 3/3/2025 Partial Approval MARTIN TAVITIAN
Final 5/2/2025 Partial Approval MARTIN TAVITIAN
Green Building Final 5/2/2025 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 5/2/2025 Approved MARTIN TAVITIAN
Wood Frame 5/2/2025 Approved MARTIN TAVITIAN
Final 6/4/2025 Partial Inspection MARTIN TAVITIAN
Final 7/2/2025 Partial Inspection MARTIN TAVITIAN
Final 7/17/2025 Partial Inspection MARTIN TAVITIAN
Final 7/22/2025 Partial Inspection MARTIN TAVITIAN