13201 W ROSE AVE 90066

Certificate Information: 13201 W ROSE AVE 90066

Application / Permit
20014-30000-02374
Plan Check / Job No.
B20WL02374
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTERATION AND ADDITION TO SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/22/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 MANUEL GARCIA
Corrections Issued 7/8/2020 MANUEL GARCIA
Quality Review Completed 7/14/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/2/2020 MANUEL GARCIA
Applicant returned to address corrections 11/19/2020 MANUEL GARCIA
Plan Check Approved 1/13/2021 MANUEL GARCIA
Issued 1/22/2021 APPLICANT
Building Plans Picked Up 1/22/2021 APPLICANT
CofO in Progress 3/10/2022 ENRIQUE MIRELES
Permit Finaled 4/6/2022 DANIEL ORRANTE
CofO Issued 4/6/2022 DANIEL ORRANTE
Permit Finaled 4/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/14/2020 DINAH GARIN
Sewer availability Cleared 8/14/2020 DINAH GARIN
Grading Pre-Inspection Cleared 8/19/2020 PATRICK MISCHLICH
Low Impact Development Cleared 10/22/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/11/2020 DINAH GARIN

Contact Information

Contractor Westside Construction; Lic. No.: 852976-B 1531 15TH STREET APT 6      SANTA MONICA, CA 90404

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/26/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/26/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/2/2021 Approved ENRIQUE MIRELES
Underground Mechanical 2/12/2021 Partial Approval JUAN VALENZUELA
Wood Frame 2/26/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 3/5/2021 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval PIERRE VEGA
Deputy Wood Construction 6/15/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Approved ENRIQUE MIRELES
HVAC-Rough 8/19/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/19/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/24/2021 Approved ENRIQUE MIRELES
HVAC-Rough 8/24/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/25/2021 Approved ENRIQUE MIRELES
Green Building Rough 8/25/2021 Approved ENRIQUE MIRELES
Insulation 9/3/2021 Approved ENRIQUE MIRELES
Drywall Nailing 9/15/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/15/2021 Approved JESUS RODRIGUEZ
Shower Pan 9/30/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/7/2021 Approved ENRIQUE MIRELES
Service/Power Release 1/11/2022 Corrections Issued ENRIQUE MIRELES
Service/Power Release 1/12/2022 Approved ENRIQUE MIRELES
Underground Mechanical 2/14/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Final 2/17/2022 Approved ENRIQUE MIRELES
Gas Test 2/17/2022 Approved ENRIQUE MIRELES
HVAC-Final 2/17/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 2/17/2022 Approved ENRIQUE MIRELES
Final 2/25/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 2/25/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/25/2022 Approved ENRIQUE MIRELES
Final 3/1/2022 Corrections Issued ENRIQUE MIRELES
Final 3/10/2022 OK to Issue CofO ENRIQUE MIRELES