2625 S AVERILL AVE 90731
Certificate Information: 2625 S AVERILL AVE 90731
- Application / Permit
- 20014-30000-02333
- Plan Check / Job No.
- B20WL02326
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 3/3/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | TARIK SAOUD |
| Corrections Issued | 7/1/2020 | TARIK SAOUD |
| Quality Review Completed | 7/7/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/3/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 10/5/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 12/10/2020 | TARIK SAOUD |
| Plan Check Approved | 2/19/2021 | TARIK SAOUD |
| Issued | 3/3/2021 | APPLICANT |
| Building Plans Picked Up | 3/4/2021 | APPLICANT |
| CofO in Progress | 2/17/2023 | JOHN KLARIN |
| Permit Finaled | 2/17/2023 | ANSON MAGLASANG |
| CofO Issued | 2/17/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/17/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/28/2020 | MARTIN FRAGOSO |
| Grading Pre-Inspection | Cleared | 10/5/2020 | TARIK SAOUD |
| Coastal Zone | Cleared | 10/14/2020 | NOAH MCCOY |
| Specific Plan | Cleared | 10/14/2020 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2020 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 11/9/2020 | CHINH DINH |
| Sewer availability | Cleared | 11/9/2020 | CHINH DINH |
Contact Information
| Contractor | M F R Construction; Lic. No.: 544888-B | 2503 CARNEGIE LANE #1 REDONDO BEACH, CA 90278 |
| Engineer | Orland,, James Curtiss; Lic. No.: C22024 | 660 18TH ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/4/2021 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/10/2021 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 5/13/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/10/2021 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 6/10/2021 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 6/10/2021 | Partial Approval | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/10/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Partial Approval | JOHN KLARIN |
| Insulation | 6/15/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 8/23/2021 | Approved | JOHN KLARIN |
| Insulation | 8/26/2021 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 8/31/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/31/2021 | Approved | JOHN KLARIN |
| Special/Order Compliance | 10/8/2021 | Corrections Issued | ANSON MAGLASANG |
| Final | 3/31/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 3/31/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 3/31/2022 | Approved | ANSON MAGLASANG |
| Final | 10/12/2022 | Corrections Issued | ANSON MAGLASANG |
| Final | 12/29/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 1/13/2023 | Corrections Issued | JOHN KLARIN |
| Final | 2/17/2023 | OK to Issue CofO | JOHN KLARIN |