5324 W WESTHAVEN ST 90016

Certificate Information: 5324 W WESTHAVEN ST 90016

Application / Permit
20014-30000-02330
Plan Check / Job No.
B20WL02324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO & CONVERSION OF (E) DET. GARAGE TO AN ADU PER ORDINANCE
Permit Issued
Issued on 2/15/2021
Issuing Office
Current Status
CofO Issued on 7/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 REZA HAGHIGHAT
Corrections Issued 7/14/2020 REZA HAGHIGHAT
Quality Review Completed 7/23/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/5/2021 REZA HAGHIGHAT
Building Plans Picked Up 2/8/2021 APPLICANT
Issued 2/15/2021 APPLICANT
CofO in Progress 7/6/2021 STUART CHAPMAN
Permit Finaled 7/16/2021 DEROLD HAUFF
CofO Issued 7/16/2021 DEROLD HAUFF
Permit Finaled 7/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 10/13/2020 RIDWAN HARDY
Address approval Cleared 11/13/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 11/13/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/18/2020 RENZ SORIANO
Sewer availability Cleared 11/18/2020 RENZ SORIANO
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG

Contact Information

Architect Verdugo,, Emilio Amado; Lic. No.: C33263 4324 GRANDVIEW BLVD      LOS ANGELES, CA 90066
Contractor Build To Sustain Inc; Lic. No.: 989835-B 319 W FAIRVIEW BLVD      INGLEWOOD, CA 90302
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/1/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 3/10/2021 Approved ROBERT VORHIS
PLUMBING-Rough 3/10/2021 Partial Approval ROBERT VORHIS
BUILDING-Rough-Frame 4/19/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 4/19/2021 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 4/19/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/19/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 4/28/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 4/28/2021 Approved STUART CHAPMAN
Insulation 5/10/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 5/10/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/12/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Approved STUART CHAPMAN
Green Building Rough 5/12/2021 Approved STUART CHAPMAN
Insulation 5/12/2021 Approved STUART CHAPMAN
Drywall Nailing 5/19/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 5/19/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/19/2021 Approved CHRISTOPHER DELLEFIELD
Final 6/10/2021 Corrections Issued DAVID FEILER
Green Building Final 6/10/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 6/10/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 6/18/2021 Not Ready for Inspection DAVID FEILER
HVAC-Final 6/18/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 6/18/2021 Not Ready for Inspection DAVID FEILER
Final 6/29/2021 Corrections Issued STUART CHAPMAN
Green Building Final 6/29/2021 Approved STUART CHAPMAN
Smoke Detectors 6/29/2021 Approved STUART CHAPMAN
Final 7/6/2021 OK to Issue CofO STUART CHAPMAN