2057 S PROSSER AVE 90025
Certificate Information: 2057 S PROSSER AVE 90025
- Application / Permit
- 20014-30000-02321
- Plan Check / Job No.
- B20WL02310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND HOUSE ADDITION WITH TWO CAR GARAGE AND ROOF TRUSS SYSTEM. TYPE VB FULLY SPRINKLERED THROUGHOUT.
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | RICARDO RAMIREZ |
| Corrections Issued | 6/29/2020 | RICARDO RAMIREZ |
| Quality Review Completed | 7/1/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 7/1/2020 | APPLICANT |
| Applicant returned to address corrections | 5/24/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/1/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 6/7/2021 | RICARDO RAMIREZ |
| Issued | 6/7/2021 | APPLICANT |
| CofO in Progress | 5/12/2022 | BRENDAN LOONEY |
| Permit Finaled | 6/13/2022 | DANIEL ORRANTE |
| CofO Issued | 6/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/6/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2020 | CATHERINE ADROVER |
| Permit | Cleared | 8/18/2020 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 8/18/2020 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/18/2020 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 5/21/2021 | JENSON LEE |
| GPI Written Notices | Cleared | 5/24/2021 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 5/24/2021 | RICARDO RAMIREZ |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 7/19/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 7/19/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 7/26/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 8/9/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 8/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 8/10/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 8/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 9/16/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 10/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 10/18/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 10/18/2021 | Approved | BRENDAN LOONEY |
| Shower Pan | 10/18/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/19/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/4/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/4/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 11/4/2021 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/4/2021 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 11/4/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/10/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 11/10/2021 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 11/10/2021 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/16/2021 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 1/14/2022 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 1/26/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/26/2022 | Approved | BRENDAN LOONEY |
| Gas Test | 4/12/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 4/12/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 4/14/2022 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 4/20/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 4/20/2022 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/29/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 4/29/2022 | Approved | BRENDAN LOONEY |
| Service/Power Release | 5/6/2022 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | BRENDAN LOONEY |
| Final | 5/11/2022 | OK to Issue CofO | BRENDAN LOONEY |
| Green Building Final | 5/11/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 5/11/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 5/11/2022 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/11/2022 | Approved | BRENDAN LOONEY |