2057 S PROSSER AVE 90025

Certificate Information: 2057 S PROSSER AVE 90025

Application / Permit
20014-30000-02321
Plan Check / Job No.
B20WL02310
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND HOUSE ADDITION WITH TWO CAR GARAGE AND ROOF TRUSS SYSTEM. TYPE VB FULLY SPRINKLERED THROUGHOUT.
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
CofO Issued on 6/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/25/2020 RICARDO RAMIREZ
Corrections Issued 6/29/2020 RICARDO RAMIREZ
Quality Review Completed 7/1/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 7/1/2020 APPLICANT
Applicant returned to address corrections 5/24/2021 RICARDO RAMIREZ
Applicant returned to address corrections 6/1/2021 RICARDO RAMIREZ
Plan Check Approved 6/7/2021 RICARDO RAMIREZ
Issued 6/7/2021 APPLICANT
CofO in Progress 5/12/2022 BRENDAN LOONEY
Permit Finaled 6/13/2022 DANIEL ORRANTE
CofO Issued 6/13/2022 DANIEL ORRANTE
Permit Finaled 6/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 8/6/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 8/18/2020 CATHERINE ADROVER
Permit Cleared 8/18/2020 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 8/18/2020 CATHERINE ADROVER
Sewer availability Cleared 8/18/2020 CATHERINE ADROVER
Miscellaneous Cleared 5/21/2021 JENSON LEE
GPI Written Notices Cleared 5/24/2021 RICARDO RAMIREZ
Grading Pre-Inspection Cleared 5/24/2021 RICARDO RAMIREZ

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
Sewer 7/19/2021 Approved GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 7/19/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 7/26/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/3/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 8/9/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 8/10/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 8/10/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 8/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 8/10/2021 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 9/16/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 10/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 10/18/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 10/18/2021 Approved BRENDAN LOONEY
Shower Pan 10/18/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 10/19/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 11/4/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 11/4/2021 Approved BRENDAN LOONEY
Green Building Rough 11/4/2021 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 11/4/2021 Partial Approval BRENDAN LOONEY
Wood Frame 11/4/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 11/10/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 11/10/2021 Partial Approval BRENDAN LOONEY
Wood Frame 11/10/2021 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 11/16/2021 Partial Approval STEPHANIE SWANSON
Insulation 1/14/2022 Conditional Approval BRENDAN LOONEY
Drywall Nailing 1/26/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 1/26/2022 Approved BRENDAN LOONEY
Gas Test 4/12/2022 Approved BRENDAN LOONEY
PLUMBING-Final 4/12/2022 Approved BRENDAN LOONEY
ELECTRICAL-Final 4/14/2022 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Final 4/20/2022 Approved BRENDAN LOONEY
HVAC-Final 4/20/2022 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 4/29/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 4/29/2022 Approved BRENDAN LOONEY
Service/Power Release 5/6/2022 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 5/11/2022 Approved BRENDAN LOONEY
Final 5/11/2022 OK to Issue CofO BRENDAN LOONEY
Green Building Final 5/11/2022 Approved BRENDAN LOONEY
HVAC-Final 5/11/2022 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved BRENDAN LOONEY
Service/Power Release 5/11/2022 Approved BRENDAN LOONEY
Smoke Detectors 5/11/2022 Approved BRENDAN LOONEY