9719 W BLANTYRE DR 90210

Certificate Information: 9719 W BLANTYRE DR 90210

Application / Permit
20014-30000-02284
Plan Check / Job No.
B20WL02286
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition and renovation to an existing 2-story sfd with attached garage.
Permit Issued
Issued on 10/6/2020
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 TARIK SAOUD
Corrections Issued 6/24/2020 TARIK SAOUD
Quality Review Completed 6/30/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/7/2020 TARIK SAOUD
Plan Check Approved 9/24/2020 TARIK SAOUD
Issued 10/6/2020 APPLICANT
Building Plans Picked Up 7/27/2022 APPLICANT
CofO in Progress 9/7/2023 BRENDAN LOONEY
Permit Finaled 9/12/2023 DANIEL ORRANTE
CofO Issued 9/12/2023 DANIEL ORRANTE
Permit Finaled 9/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 7/9/2020 ANNA VIDAL
CPC Cleared 7/9/2020 ANNA VIDAL
BHO/Hillside ordinance Cleared 7/14/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 7/14/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 7/14/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 7/14/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 7/14/2020 DINAH GARIN
Sewer availability Cleared 7/14/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/17/2020 DINAH GARIN
Hydrant and Access approval Cleared 8/6/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 8/7/2020 TARIK SAOUD
Specific Plan Cleared 8/20/2020 TRACY WILLIAMS
Specific Plan Cleared 8/20/2020 TRACY WILLIAMS
Low Impact Development Cleared 9/11/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/18/2020 DINAH GARIN

Contact Information

Architect Elmanovich,, Vladimir; Lic. No.: C25822 16987 ENCINO HILLS DRIVE      ENCINO, CA 91436
Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2021 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 12/8/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/10/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 1/27/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 1/31/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 5/16/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 5/25/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/27/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/3/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/3/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 7/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 7/8/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/14/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 8/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 10/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 10/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/3/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 10/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 10/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 10/7/2022 Approved CARLOS MATAMOROS
Drywall Nailing 10/31/2022 Approved MICHAEL PELHAM
Shower Pan 12/23/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/30/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 2/13/2023 Corrections Issued CHRISTOPHER WILSON
Sewer 2/15/2023 Approved GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/16/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/16/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 6/23/2023 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 6/23/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 6/26/2023 Approved BRENDAN LOONEY
PLUMBING-Final 6/26/2023 Approved BRENDAN LOONEY
HVAC-Final 6/29/2023 Corrections Issued BRENDAN LOONEY
Final 7/7/2023 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 7/7/2023 No Access for Inspection BRENDAN LOONEY
Green Building Final 7/7/2023 No Access for Inspection BRENDAN LOONEY
HVAC-Final 7/7/2023 No Access for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 7/7/2023 No Access for Inspection BRENDAN LOONEY
HVAC-Final 7/11/2023 Approved BRENDAN LOONEY
Final 8/30/2023 OK to Issue CofO BRENDAN LOONEY
Footing/Foundation/Slab 8/30/2023 Approved BRENDAN LOONEY
Green Building Final 8/30/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 8/30/2023 Approved BRENDAN LOONEY