848 N GLENMERE WAY 90049

Certificate Information: 848 N GLENMERE WAY 90049

Application / Permit
20014-30000-02264
Plan Check / Job No.
B20WL02261
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
CofO Issued on 2/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 SERGIO SILVA
Corrections Issued 6/23/2020 SERGIO SILVA
Quality Review Completed 6/29/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/31/2020 SERGIO SILVA
Applicant returned to address corrections 8/3/2020 SERGIO SILVA
Plan Check Approved 9/2/2020 SERGIO SILVA
Issued 9/16/2020 APPLICANT
Building Plans Picked Up 9/16/2020 APPLICANT
CofO in Progress 1/31/2022 JUAN VALENZUELA
Permit Finaled 2/26/2022 DANIEL ORRANTE
CofO Issued 2/26/2022 DANIEL ORRANTE
Permit Finaled 2/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 8/3/2020 SERGIO SILVA
BHO/Hillside ordinance Cleared 8/7/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 8/7/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 8/7/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 8/7/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 8/7/2020 DINAH GARIN
Permit Cleared 8/12/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 8/12/2020 DINAH GARIN
Sewer availability Cleared 8/12/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/14/2020 DINAH GARIN
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG
Trees in Parkway Cleared 8/20/2020 JOHN KIM
Distance to fire station Cleared 8/25/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 9/2/2020 SERGIO SILVA
Green Code Cleared 9/2/2020 SERGIO SILVA

Contact Information

Contractor Dixon Construction Inc; Lic. No.: 706524-B 3169 MOUNTAIN VIEW AVE      LOS ANGELES, CA 90066
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Yamashita,, Mark Alan; Lic. No.: L7155 6718 BIANCA AVE      LAKE BALBOA, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/27/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 11/2/2020 Partial Approval JOHN KIDWELL
FLOOD-Proofing Certificate 11/12/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 11/12/2020 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 1/26/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/26/2021 Approved JUAN VALENZUELA
Deputy Wood Construction 4/7/2021 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/15/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 4/26/2021 Corrections Issued JUAN VALENZUELA
HVAC-Rough 4/26/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 4/30/2021 Approved JUAN VALENZUELA
HVAC-Rough 4/30/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 5/11/2021 Approved JUAN VALENZUELA
Green Building Rough 5/11/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/11/2021 Partial Approval JUAN VALENZUELA
Verify Sprinkler Sign Off 5/11/2021 Approved JUAN VALENZUELA
Insulation 5/26/2021 Approved JUAN VALENZUELA
Drywall Nailing 6/2/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/8/2021 Partial Approval AMY COLIN
Shower Pan 6/8/2021 Approved AMY COLIN
Interior/Exterior Lathing 6/10/2021 Approved JUAN VALENZUELA
Underground Mechanical 10/20/2021 Approved ANDREW NAVE
Gas Test 11/23/2021 Approved JUAN VALENZUELA
HVAC-Final 12/7/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 12/8/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 12/10/2021 Approved JUAN VALENZUELA
Green Building Final 12/15/2021 Approved JUAN VALENZUELA
HVAC-Final 12/15/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 12/15/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 1/31/2022 Approved JUAN VALENZUELA
Final 1/31/2022 OK to Issue CofO JUAN VALENZUELA