8026 S ALVERSTONE AVE 90045

Certificate Information: 8026 S ALVERSTONE AVE 90045

Application / Permit
20014-30000-02198
Plan Check / Job No.
B20WL02195
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition to (E) 1 story SFD.
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
Issued on 1/5/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 7/22/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 7/29/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 10/4/2020 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 10/5/2020 APPLICANT
Issued 1/5/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/9/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 9/9/2020 ANTHONY MAINEZ
Sewer availability Cleared 9/9/2020 ANTHONY MAINEZ

Contact Information

Contractor Addazero Corp; Lic. No.: 1019955-B 5399 PLAYA VISTA DR #E433      PLAYA VISTA, CA 90094
Engineer Galbreath,, Sean Martin; Lic. No.: S5653 1386 EAST WALNUT STREET SUITE 202      PASADENA, CA 91106

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/11/2021 Approved JUAN VALENZUELA
Deputy Drilled-In Anchors 1/22/2021 Partial Approval PIERRE VEGA
Excavation/Setback/Form/Re-Bar 1/25/2021 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 1/26/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 2/8/2021 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 2/11/2021 Conditional Approval EVAN COOPER
Deputy Wood Construction 3/26/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval KENNETH NAGLE
PLUMBING-Rough 4/7/2021 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 4/13/2021 Approved PIERRE VEGA
ELECTRICAL-Rough 4/22/2021 Corrections Issued KENNETH NAGLE
ELECTRICAL-Rough 5/5/2021 Approved ENRIQUE MIRELES
Wood Frame 5/5/2021 Not Ready for Inspection ENRIQUE MIRELES
Deputy Wood Construction 5/14/2021 Conditional Approval WILLIAM ROSE
Interior/Exterior Lathing 5/21/2021 No Access for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/9/2021 Partial Approval JOHNNY MIRANDA
Insulation 7/12/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 7/14/2021 Corrections Issued JOHNNY MIRANDA
Green Building Rough 7/14/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 7/19/2021 Conditional Approval BRENDAN LOONEY
HVAC-Rough 7/19/2021 Corrections Issued BRENDAN LOONEY
Insulation 7/19/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 7/28/2021 Approved ENRIQUE MIRELES
Insulation 7/28/2021 Approved ENRIQUE MIRELES
Drywall Nailing 8/4/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/24/2021 Partial Approval JUAN VALENZUELA
Shower Pan 8/24/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 12/10/2021 Approved JOHN KAYON
HVAC-Final 12/10/2021 Approved JOHN KAYON
PLUMBING-Final 12/20/2021 Approved JOHN KAYON
BUILDING-Rough-Frame 2/25/2022 Approved ENRIQUE MIRELES
Final 2/25/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/25/2022 Approved ENRIQUE MIRELES
Green Building Final 2/25/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/25/2022 Approved ENRIQUE MIRELES
Final 3/24/2022 Partial Approval JESUS RODRIGUEZ