2212-2218 W LAVERNA AVE 90041
Certificate Information: 2212-2218 W LAVERNA AVE 90041
- Application / Permit
- 20014-30000-02196
- Plan Check / Job No.
- B20WL02192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 2ND STORY, 1 UNIT ADDITION TO EXISTING 2-STORY 3-UNIT APARTMENT BUILDING WITH ATTACHED 4-CAR GARAGE
- Permit Issued
- Issued on 1/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | TARIK SAOUD |
| Corrections Issued | 6/30/2020 | TARIK SAOUD |
| Quality Review Completed | 7/6/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/5/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 10/16/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 11/2/2020 | TARIK SAOUD |
| Green Plans Picked Up | 11/24/2020 | APPLICANT |
| Plan Check Approved | 12/17/2020 | TARIK SAOUD |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Issued | 1/18/2021 | APPLICANT |
| CofO in Progress | 4/12/2024 | RAFAEL CORTES |
| CofO Issued | 4/12/2024 | ERNESTO CORRAL |
| Permit Finaled | 4/12/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2020 | WALLIE JONG |
| DAS Clearance | Cleared | 7/27/2020 | SOMKIAT SUPANYACHOTSKUL |
| Sewer availability | Cleared | 7/31/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 8/5/2020 | KURT CORRAL |
| Tenant Habitability Plan | Cleared | 9/18/2020 | PHILLIP MUNGUIA |
| Low Impact Development | Cleared | 10/30/2020 | MITESH PATEL |
| Grading Pre-Inspection | Cleared | 11/2/2020 | TARIK SAOUD |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2020 | WALLIE JONG |
| Green Code | Cleared | 11/17/2020 | RICHARD GARCIA |
Contact Information
| Architect | Gomez,, Leonardo; Lic. No.: C30238 | 4342 ALLA ROAD LOS ANGELES, CA 90066 |
| Contractor | H B Home Bridge Inc; Lic. No.: 902733-B | 2054 SCENIC RIDGE DR CHINO HILLS, CA 91709 |
| Engineer | Chou,, Shen-Sheng Albert; Lic. No.: S2516 | 712 MARYLIE LANE WALNUT, CA 91789 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Partial Approval | RONALD PACHECO |
| Pre-Inspection | 6/3/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 6/3/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Rough | 6/11/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 6/11/2021 | Corrections Issued | MARK FERRARI |
| Green Building Rough | 8/19/2021 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 8/19/2021 | Not Ready for Inspection | LANNY MERRICK |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 9/30/2021 | Partial Approval | DANIEL COLLINS |
| Green Building Rough | 5/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 5/18/2022 | Corrections Issued | MARK FERRARI |
| Green Building Rough | 6/2/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 6/2/2022 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 6/8/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Wood Construction | 6/21/2022 | Conditional Approval | MARK FERRARI |
| Green Building Rough | 6/27/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 6/27/2022 | Partial Inspection | MARK FERRARI |
| Green Building Rough | 7/1/2022 | Approved | MARK FERRARI |
| Wood Frame | 7/1/2022 | Partial Approval | MARK FERRARI |
| Insulation | 7/20/2022 | Approved | MARK FERRARI |
| Wood Frame | 7/20/2022 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 8/4/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 8/25/2022 | Corrections Issued | BRUCE CAMPBELL |
| Drywall Nailing | 9/2/2022 | Approved | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 9/2/2022 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 9/15/2022 | Partial Approval | MARK FERRARI |
| Final | 7/12/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 7/12/2023 | Approved | RAFAEL CORTES |
| Green Building Final | 7/12/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 7/12/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 7/12/2023 | Approved | RAFAEL CORTES |
| Final | 9/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 9/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 9/11/2023 | Approved | RAFAEL CORTES |
| Final | 12/6/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 12/6/2023 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | RAFAEL CORTES |
| Final | 1/11/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 4/12/2024 | OK to Issue CofO | RAFAEL CORTES |