8436 N OAKDALE AVE 91306
Certificate Information: 8436 N OAKDALE AVE 91306
- Application / Permit
- 20014-30000-02194
- Plan Check / Job No.
- B20WL02187
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N)Detached ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | ALFREDO JARA |
| Corrections Issued | 6/16/2020 | ALFREDO JARA |
| Quality Review Completed | 6/23/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/31/2021 | ALFREDO JARA |
| Plan Check Approved | 2/7/2022 | ALFREDO JARA |
| Issued | 3/24/2022 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| CofO in Progress | 4/10/2023 | SEAN WIRCH |
| CofO Issued | 5/17/2023 | MICHAEL SMITH |
| Permit Finaled | 5/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 8/31/2020 | RIDWAN HARDY |
| Miscellaneous | Cleared | 9/25/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 2/23/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 2/23/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/24/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/19/2022 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Approved | JEFFREY PARD |
| Underground Mechanical | 7/29/2022 | Approved | JEFFREY PARD |
| Wood Frame | 7/29/2022 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 8/24/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 8/24/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/24/2022 | Corrections Issued | JEFFREY PARD |
| Shower Pan | 8/24/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | JEFFREY PARD |
| Gas Test | 10/7/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 10/7/2022 | Approved | JEFFREY PARD |
| Wood Frame | 10/7/2022 | Approved | JEFFREY PARD |
| Insulation | 10/14/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/14/2022 | Partial Approval | KRISTEN CAUSEY |
| Drywall Nailing | 11/1/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 11/1/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/1/2022 | Partial Approval | JOHN KIDWELL |
| Gas Test | 1/18/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/18/2023 | Approved | KRISTEN CAUSEY |
| Final | 3/2/2023 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/2/2023 | Approved | DAVID SANDOVAL |
| Green Building Final | 3/2/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/2/2023 | SGSOV Not Ready | DAVID SANDOVAL |
| Service/Power Release | 3/2/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 3/2/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/17/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 3/17/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/17/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 3/17/2023 | Partial Inspection | MORRIS JACKSON |
| Service/Power Release | 4/3/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 4/7/2023 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 4/7/2023 | Approved | SEAN WIRCH |
| Service/Power Release | 4/7/2023 | Approved | SEAN WIRCH |