2157 N MORENO DR 90039
Certificate Information: 2157 N MORENO DR 90039
- Application / Permit
- 20014-30000-02192
- Plan Check / Job No.
- B20WL02185
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF ATTIC SPACE INTO LIVABLE SPACE TO THE (E) SFD AND REMODEL (E) KITCHEN & BATHROOMS.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | MANUEL GARCIA |
| Corrections Issued | 6/24/2020 | MANUEL GARCIA |
| Quality Review Completed | 6/30/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/2/2020 | MANUEL GARCIA |
| Plan Check Approved | 10/13/2020 | MANUEL GARCIA |
| Issued | 11/2/2020 | APPLICANT |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| CofO in Progress | 9/28/2021 | JOSEPH MCGARRY |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/9/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/9/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/9/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/9/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/10/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/16/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 7/31/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/4/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/4/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 3/4/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/4/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/4/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/23/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 3/23/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 3/23/2021 | Conditional Approval | JOSEPH MCGARRY |
| Shower Pan | 3/23/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/1/2021 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 4/1/2021 | No Access for Inspection | ELMER BLAND |
| Drywall Nailing | 4/1/2021 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/1/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 7/12/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/12/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/17/2021 | Approved | JOSEPH MCGARRY |
| Final | 9/17/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 9/17/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 9/17/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 9/17/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 9/17/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 9/17/2021 | Approved | JOSEPH MCGARRY |