1221 W 27TH ST 90731

Certificate Information: 1221 W 27TH ST 90731

Application / Permit
20014-30000-02110
Plan Check / Job No.
B20WL02114
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL (E) SFD.
Permit Issued
Issued on 11/29/2021
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 MANUEL GARCIA
Corrections Issued 6/23/2020 MANUEL GARCIA
Quality Review Completed 6/29/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/18/2020 MANUEL GARCIA
Applicant returned to address corrections 1/22/2021 MANUEL GARCIA
Applicant returned to address corrections 2/23/2021 MANUEL GARCIA
Applicant returned to address corrections 3/2/2021 MANUEL GARCIA
Applicant returned to address corrections 3/3/2021 MANUEL GARCIA
Applicant returned to address corrections 4/29/2021 SERGIO SILVA
Plan Check Approved 11/16/2021 MANUEL GARCIA
Issued 11/29/2021 APPLICANT
Building Plans Picked Up 11/30/2021 APPLICANT
CofO in Progress 2/21/2024 JAMES CHAVEZ
Permit Finaled 2/22/2024 ANSON MAGLASANG
CofO Issued 2/22/2024 ANSON MAGLASANG
Permit Finaled 2/22/2024 ANSON MAGLASANG

Permit Application Clearance Information

Sewer availability Cleared 7/23/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/24/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 8/12/2020 ERIK BEASLEY
Grading Pre-Inspection Cleared 8/14/2020 KIRK LINKLATER
Miscellaneous Cleared 8/26/2020 RUBEN VASQUEZ
Construction near power lines Cleared 9/30/2020 RIDWAN HARDY
Coastal Zone Cleared 10/7/2020 RUBEN VASQUEZ
Low Impact Development Cleared 10/25/2021 LONDY ALVARADO

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/14/2022 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/17/2022 Approved ANSON MAGLASANG
Footing/Foundation/Slab 2/17/2022 Approved ANSON MAGLASANG
Sewer 3/1/2022 Partial Approval ANSON MAGLASANG
Wood Frame 3/1/2022 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 5/11/2022 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 5/13/2022 Not Ready for Inspection EUGENE CASSIDY
Gas Test 5/13/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 5/13/2022 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 5/13/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 5/13/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 5/17/2022 Partial Approval ANSON MAGLASANG
Gas Test 5/17/2022 Approved ANSON MAGLASANG
Green Building Rough 5/17/2022 Approved ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 5/17/2022 Approved ANSON MAGLASANG
Verify Sprinkler Sign Off 5/17/2022 Approved ANSON MAGLASANG
Insulation 5/20/2022 Approved ANSON MAGLASANG
Drywall Nailing 6/1/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 6/1/2022 Approved ANSON MAGLASANG
Service/Power Release 6/1/2022 Not Ready for Inspection ANSON MAGLASANG
Shower Pan 6/1/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 1/17/2023 Approved JOHN KLARIN
Final 1/17/2023 Corrections Issued JOHN KLARIN
Green Building Final 1/17/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 1/17/2023 Approved JOHN KLARIN
Final 2/16/2024 OK to Issue CofO JAMES CHAVEZ
Green Building Final 2/16/2024 Approved JAMES CHAVEZ