222 N GLENROY AVE 90049
Certificate Information: 222 N GLENROY AVE 90049
- Application / Permit
- 20014-30000-02061
- Plan Check / Job No.
- B20WL02090
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND MAYOR ALTERATION/REPAIR TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS. 1ST AND 2ND FLOOR ADDITION TO SINGLE FAMILY DWELLING, AND ADDITION OF ATTACHED GARAGE ON 1ST FLOOR.
- Permit Issued
- Issued on 7/12/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | SERGIO SILVA |
| Corrections Issued | 6/16/2020 | SERGIO SILVA |
| Quality Review Completed | 6/23/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/8/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 12/14/2020 | SERGIO SILVA |
| Building Plans Picked Up | 12/15/2020 | APPLICANT |
| Applicant returned to address corrections | 4/12/2021 | SERGIO SILVA |
| Plan Check Approved | 6/9/2021 | SERGIO SILVA |
| Issued | 7/12/2021 | APPLICANT |
| CofO in Progress | 6/14/2024 | CARLOS MATAMOROS |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| CofO Issued | 6/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/15/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 6/15/2020 | SERGIO SILVA |
| CPC | Cleared | 6/25/2020 | LAUREN PADICK |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | DINAH GARIN |
| Permit | Cleared | 6/30/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/14/2020 | DINAH GARIN |
| Trees in Parkway | Cleared | 8/13/2020 | JOHN KIM |
| Green Code | Cleared | 10/8/2020 | SERGIO SILVA |
| BHO/Hillside ordinance | Cleared | 11/23/2020 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 3/3/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | DENNIS BRAGIN |
| Distance to fire station | Cleared | 5/24/2021 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 5/24/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/22/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/23/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/27/2022 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/17/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/1/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/26/2022 | Corrections Issued | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 10/7/2022 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/10/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 1/10/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/10/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/10/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/15/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 2/15/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 2/15/2023 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 2/15/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 2/15/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 2/28/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/9/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/9/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/19/2023 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 8/9/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/5/2023 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 12/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 12/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/7/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 12/7/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 12/7/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 12/7/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/4/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/26/2024 | Approved | CARLOS MATAMOROS |
| Final | 4/26/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 4/26/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 4/26/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/26/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 4/26/2024 | Approved | CARLOS MATAMOROS |
| Final | 6/14/2024 | OK to Issue CofO | CARLOS MATAMOROS |