2200 S MANTIS AVE 90732

Certificate Information: 2200 S MANTIS AVE 90732

Application / Permit
20014-30000-02045
Plan Check / Job No.
B20WL02073
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (N) ATTACHED GARAGE AND CONVERT (E) GARAGE TO A BEDROOM AND INTERIOR REMODEL TO EXISTING 1-STORY SFD.
Permit Issued
Issued on 4/4/2022
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 TARIK SAOUD
Corrections Issued 6/22/2020 TARIK SAOUD
Quality Review Completed 6/29/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/30/2020 APPLICANT
Applicant returned to address corrections 2/8/2021 TARIK SAOUD
Plan Check Approved 9/7/2021 TARIK SAOUD
Issued 4/4/2022 APPLICANT
CofO in Progress 4/2/2026 JOSEPH MCGARRY
Permit Finaled 4/2/2026 ANSON MAGLASANG
CofO Issued 4/2/2026 ANSON MAGLASANG
Permit Finaled 4/2/2026 ANSON MAGLASANG

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/22/2020 CHINH DINH
BHO/Hillside ordinance Cleared 7/22/2020 CHINH DINH
BHO/Hillside ordinance Cleared 7/22/2020 CHINH DINH
BHO/Hillside ordinance Cleared 7/22/2020 CHINH DINH
BHO/Hillside ordinance Cleared 7/22/2020 CHINH DINH
Roof/Waste drainage to street Cleared 7/22/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 7/27/2020 CHINH DINH
Construction near power lines Cleared 11/20/2020 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/8/2021 TARIK SAOUD
Low Impact Development Cleared 6/10/2021 JORGE MEJIA LEMUS

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Calco Grading Inc; Lic. No.: 1047667-A 3637 GREVE DR      RANCHO PALOS VERDES, CA 90275
Engineer Lee,, Shyan-Chyun Tony; Lic. No.: C44045 17834 BAILEY DRIVE      TORRANCE, CA 90504
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2022 Partial Approval ANSON MAGLASANG
Pre-Inspection 4/19/2022 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 5/26/2022 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 6/2/2022 Partial Approval ANSON MAGLASANG
Footing/Foundation/Slab 9/6/2022 Approved EUGENE CASSIDY
Special/Order Compliance 10/26/2022 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 3/22/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Approved JAMES CHAVEZ
Green Building Rough 3/22/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 3/22/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 3/22/2023 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 5/9/2023 Partial Inspection JAMES CHAVEZ
ELECTRICAL-Rough 5/9/2023 Approved JAMES CHAVEZ
Green Building Rough 5/9/2023 Approved JAMES CHAVEZ
HVAC-Rough 5/9/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 5/9/2023 Approved JAMES CHAVEZ
Insulation 5/26/2023 Approved JAMES CHAVEZ
Drywall Nailing 6/6/2023 Approved ANSON MAGLASANG
Interior/Exterior Lathing 6/6/2023 Partial Approval ANSON MAGLASANG
Shower Pan 1/11/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 2/9/2024 No Access for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 2/20/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Final 3/4/2024 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 3/4/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/19/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Final 4/3/2025 Approved JOSEPH MCGARRY
HVAC-Final 4/3/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 9/19/2025 Approved JOSEPH MCGARRY
Final 9/19/2025 Corrections Issued JOSEPH MCGARRY
Green Building Final 9/19/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 9/19/2025 Approved JOSEPH MCGARRY
Final 11/26/2025 Not Ready for Inspection JOSEPH MCGARRY
Final 3/27/2026 Not Ready for Inspection JOSEPH MCGARRY
Final 4/1/2026 OK to Issue CofO JOSEPH MCGARRY