2200 S MANTIS AVE 90732
Certificate Information: 2200 S MANTIS AVE 90732
- Application / Permit
- 20014-30000-02045
- Plan Check / Job No.
- B20WL02073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (N) ATTACHED GARAGE AND CONVERT (E) GARAGE TO A BEDROOM AND INTERIOR REMODEL TO EXISTING 1-STORY SFD.
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | TARIK SAOUD |
| Corrections Issued | 6/22/2020 | TARIK SAOUD |
| Quality Review Completed | 6/29/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/30/2020 | APPLICANT |
| Applicant returned to address corrections | 2/8/2021 | TARIK SAOUD |
| Plan Check Approved | 9/7/2021 | TARIK SAOUD |
| Issued | 4/4/2022 | APPLICANT |
| CofO in Progress | 4/2/2026 | JOSEPH MCGARRY |
| Permit Finaled | 4/2/2026 | ANSON MAGLASANG |
| CofO Issued | 4/2/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/2/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/22/2020 | CHINH DINH |
| BHO/Hillside ordinance | Cleared | 7/22/2020 | CHINH DINH |
| BHO/Hillside ordinance | Cleared | 7/22/2020 | CHINH DINH |
| BHO/Hillside ordinance | Cleared | 7/22/2020 | CHINH DINH |
| BHO/Hillside ordinance | Cleared | 7/22/2020 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 7/22/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | CHINH DINH |
| Construction near power lines | Cleared | 11/20/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 2/8/2021 | TARIK SAOUD |
| Low Impact Development | Cleared | 6/10/2021 | JORGE MEJIA LEMUS |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Calco Grading Inc; Lic. No.: 1047667-A | 3637 GREVE DR RANCHO PALOS VERDES, CA 90275 |
| Engineer | Lee,, Shyan-Chyun Tony; Lic. No.: C44045 | 17834 BAILEY DRIVE TORRANCE, CA 90504 |
| Engineer | Shirley,, Peter Franklin; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/14/2022 | Partial Approval | ANSON MAGLASANG |
| Pre-Inspection | 4/19/2022 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 5/26/2022 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Rough | 6/2/2022 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/6/2022 | Approved | EUGENE CASSIDY |
| Special/Order Compliance | 10/26/2022 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 3/22/2023 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 3/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 3/22/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 3/22/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/9/2023 | Partial Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/9/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 5/9/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 5/9/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 5/9/2023 | Approved | JAMES CHAVEZ |
| Insulation | 5/26/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/6/2023 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 6/6/2023 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 1/11/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 2/9/2024 | No Access for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 2/20/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Final | 3/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 3/4/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/19/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/3/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 4/3/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/19/2025 | Approved | JOSEPH MCGARRY |
| Final | 9/19/2025 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 9/19/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 9/19/2025 | Approved | JOSEPH MCGARRY |
| Final | 11/26/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 3/27/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 4/1/2026 | OK to Issue CofO | JOSEPH MCGARRY |