1185 W 30TH PL 90007

Certificate Information: 1185 W 30TH PL 90007

Application / Permit
20014-30000-01691
Plan Check / Job No.
B20WL01788
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to and conversion of (e) detached garage to an accessory dwelling unit per ordinance.
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
CofO Issued on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 REZA HAGHIGHAT
Corrections Issued 5/13/2020 REZA HAGHIGHAT
Quality Review Completed 5/19/2020 TARIK SAOUD
Applicant returned to address corrections 8/13/2020 REZA HAGHIGHAT
Green Plans Picked Up 9/2/2020 APPLICANT
Plan Check Approved 9/17/2020 REZA HAGHIGHAT
Issued 9/29/2020 APPLICANT
Building Plans Picked Up 9/30/2020 APPLICANT
CofO in Progress 3/3/2021 KATHRYN BUTTERWORTH
CofO Issued 3/24/2022 DEROLD HAUFF
Permit Finaled 3/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/28/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 5/28/2020 JUAN ASHTON
Sewer availability Cleared 5/28/2020 JUAN ASHTON
HPOZ Cleared 6/1/2020 DANIEL MATA
Specific Plan Cleared 6/1/2020 DANIEL MATA
ZA Case Cleared 6/1/2020 DANIEL MATA
ZI Cleared 6/1/2020 DANIEL MATA
ZI Cleared 6/1/2020 DANIEL MATA
ZI Cleared 6/1/2020 HELEN JADALI
Construction near power lines Cleared 6/22/2020 OSCAR CASTRO
Roof/Waste drainage to street Cleared 7/9/2020 RENZ SORIANO
Hydrant and Access approval Cleared 7/29/2020 KURT CORRAL
Green Code Cleared 9/2/2020 REZA HAGHIGHAT

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 5919 S CROSFT AVENUE      LOS ANGELES, CA 90056
Contractor Owner-Builder       ,
Engineer Kang,, Danniel; Lic. No.: S6242 633 E 223RD ST B      CARSON, CA 90745

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2020 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 10/9/2020 Corrections Issued SCOTT FINNILA
Pre-Inspection 10/9/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 10/13/2020 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 10/13/2020 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 10/13/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 10/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 10/30/2020 Approved KATHRYN BUTTERWORTH
Wood Frame 10/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/5/2020 Partial Approval DAVID CHAN
Green Building Rough 11/6/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/6/2020 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 11/6/2020 Approved KATHRYN BUTTERWORTH
Insulation 11/10/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 11/17/2020 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 1/5/2021 Approved KATHRYN BUTTERWORTH
Final 1/5/2021 OK to Issue CofO KATHRYN BUTTERWORTH
Green Building Final 1/5/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 1/5/2021 Approved KATHRYN BUTTERWORTH