6442 W WYNKOOP ST 90045
Certificate Information: 6442 W WYNKOOP ST 90045
- Application / Permit
- 20014-30000-01629
- Plan Check / Job No.
- B20WL01724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL WITH ONE STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING. "COMPLY WITH DEPARTMENT ORDER. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 5/28/2020
- Issuing Office
- Current Status
- CofO Issued on 4/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | RICARDO RAMIREZ |
| Corrections Issued | 4/29/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 5/19/2020 | RICARDO RAMIREZ |
| Issued | 5/28/2020 | APPLICANT |
| Building Plans Picked Up | 6/9/2020 | APPLICANT |
| CofO in Progress | 4/9/2021 | MARIAN PODPORA |
| Permit Finaled | 4/14/2021 | BRUCE TODD |
| CofO Issued | 4/14/2021 | BRUCE TODD |
| Permit Finaled | 4/14/2021 | BRUCE TODD |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/12/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 5/19/2020 | RICARDO RAMIREZ |
| Hold | Not Cleared | 4/14/2021 | Department of Building and Safety |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2020 | Approved | MARIAN PODPORA |
| Footing/Foundation/Slab | 6/2/2020 | Approved | MARIAN PODPORA |
| METHANE-Barrier | 6/2/2020 | Approved | MARIAN PODPORA |
| METHANE-Subgrade | 6/2/2020 | Approved | MARIAN PODPORA |
| Wood Frame | 6/10/2020 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2020 | Partial Approval | RYAN BARNES |
| ELECTRICAL-Rough | 9/1/2020 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2020 | Partial Approval | MARIAN PODPORA |
| HVAC-Rough | 9/1/2020 | Partial Approval | MARIAN PODPORA |
| PLUMBING-Rough | 9/1/2020 | Partial Approval | MARIAN PODPORA |
| ELECTRICAL-Rough | 9/3/2020 | Partial Approval | MARIAN PODPORA |
| HVAC-Rough | 9/3/2020 | Corrections Issued | MARIAN PODPORA |
| PLUMBING-Rough | 9/3/2020 | Approved | MARIAN PODPORA |
| Wood Frame | 9/4/2020 | Not Ready for Inspection | MARIAN PODPORA |
| Insulation | 9/16/2020 | Conditional Approval | MARIAN PODPORA |
| Wood Frame | 9/16/2020 | Conditional Approval | MARIAN PODPORA |
| Service/Power Release | 9/18/2020 | Approved | MARIAN PODPORA |
| Shower Pan | 9/18/2020 | Approved | MARIAN PODPORA |
| Drywall Nailing | 9/22/2020 | Approved | MARIAN PODPORA |
| Insulation | 10/14/2020 | Approved | MARIAN PODPORA |
| Interior/Exterior Lathing | 10/14/2020 | Partial Approval | MARIAN PODPORA |
| ELECTRICAL-Final | 3/5/2021 | Corrections Issued | MARIAN PODPORA |
| HVAC-Final | 3/5/2021 | Corrections Issued | MARIAN PODPORA |
| BUILDING-Rough-Frame | 3/24/2021 | Approved | MARIAN PODPORA |
| Final | 3/24/2021 | Corrections Issued | MARIAN PODPORA |
| Green Building Final | 3/24/2021 | Approved | MARIAN PODPORA |
| Green Building Rough | 3/24/2021 | Approved | MARIAN PODPORA |
| METHANE-Final | 3/24/2021 | Approved | MARIAN PODPORA |
| METHANE-Rough | 3/24/2021 | Approved | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 3/24/2021 | SGSOV Not Ready | MARIAN PODPORA |
| Smoke Detectors | 3/24/2021 | Approved | MARIAN PODPORA |
| Final | 4/5/2021 | Not Ready for Inspection | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Not Ready | MARIAN PODPORA |
| HVAC-Final | 4/7/2021 | Corrections Issued | MARIAN PODPORA |
| Final | 4/8/2021 | Corrections Issued | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | MARIAN PODPORA |
| ELECTRICAL-Final | 4/9/2021 | Approved | MARIAN PODPORA |
| Final | 4/9/2021 | OK to Issue CofO | MARIAN PODPORA |
| HVAC-Final | 4/9/2021 | Approved | MARIAN PODPORA |
| PLUMBING-Final | 4/9/2021 | Approved | MARIAN PODPORA |