19220 W STRATHERN ST 91335

Certificate Information: 19220 W STRATHERN ST 91335

Application / Permit
20014-30000-01628
Plan Check / Job No.
B20WL01720
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Accessory dwelling unit and garage addition to the existing detached carport and workshop per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 12/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 MARJAN SHENASI
Corrections Issued 5/12/2020 MARJAN SHENASI
Quality Review Completed 5/19/2020 TARIK SAOUD
Green Plans Picked Up 7/13/2020 APPLICANT
Applicant returned to address corrections 11/10/2020 MARJAN SHENASI
Plan Check Approved 12/4/2020 MARJAN SHENASI
No Progress 12/7/2020 MARJAN SHENASI
Building Plans Picked Up 12/7/2020 APPLICANT
Issued 12/21/2020 APPLICANT
CofO in Progress 4/13/2021 VINCENT HANLEY
Permit Finaled 4/16/2021 MICHAEL SMITH
CofO Issued 4/16/2021 MICHAEL SMITH
Permit Finaled 4/16/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/27/2020 GUILLERMO PETRA
Green Code Cleared 7/8/2020 VIVIAN LAO
Eng Process Fee Ord 176,300 Cleared 7/14/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/14/2020 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 8/20/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/23/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/29/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/23/2020 Approved VINCENT HANLEY
PLUMBING-Rough 12/23/2020 Partial Approval VINCENT HANLEY
Sewer 12/23/2020 Approved VINCENT HANLEY
Underground Mechanical 12/23/2020 Partial Approval VINCENT HANLEY
Deputy Wood Construction 1/12/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 1/21/2021 Approved VINCENT HANLEY
HVAC-Rough 1/21/2021 Approved VINCENT HANLEY
PLUMBING-Rough 1/21/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Approved VINCENT HANLEY
Green Building Rough 1/25/2021 Not Ready for Inspection VINCENT HANLEY
Insulation 1/25/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/27/2021 Approved VINCENT HANLEY
Drywall Nailing 1/27/2021 Approved VINCENT HANLEY
Green Building Rough 1/27/2021 Approved VINCENT HANLEY
Insulation 1/27/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/27/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 1/29/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/29/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 4/13/2021 Approved VINCENT HANLEY
Final 4/13/2021 OK to Issue CofO VINCENT HANLEY
Green Building Final 4/13/2021 Approved VINCENT HANLEY
HVAC-Final 4/13/2021 Approved VINCENT HANLEY
PLUMBING-Final 4/13/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/13/2021 Approved VINCENT HANLEY
Smoke Detectors 4/13/2021 Approved VINCENT HANLEY