1603 N MICHELTORENA ST 90026
Certificate Information: 1603 N MICHELTORENA ST 90026
- Application / Permit
- 20014-30000-01618
- Plan Check / Job No.
- B20WL01708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION IN REAR OF BUILDING OF EXISTING 2-STORY TYPE VB SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/12/2021
- Issuing Office
- Current Status
- Issued on 1/12/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2020 | SERGIO SILVA |
| Corrections Issued | 5/20/2020 | SERGIO SILVA |
| Quality Review Completed | 5/26/2020 | TARIK SAOUD |
| Green Plans Picked Up | 9/8/2020 | APPLICANT |
| Applicant returned to address corrections | 9/22/2020 | SERGIO SILVA |
| Plan Check Approved | 1/4/2021 | SERGIO SILVA |
| Issued | 1/12/2021 | APPLICANT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | CECILIO NAVARRO |
| Permit | Cleared | 8/6/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 8/6/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/6/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 8/24/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 8/26/2020 | VIVIAN LAO |
| Tenant Habitability Plan | Cleared | 12/7/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barajas,, George Luis; Lic. No.: L8399 | 3635 SHADOW GROVE RD PASADENA, CA 91107 |
| Engineer | Chikhale,, Jonathan William; Lic. No.: C78893 | 2820 MILITARY AVENUE LOS ANGELES, CA 90064 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2021 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/5/2021 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/5/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/22/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 3/22/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2021 | Approved | SCOTT FINNILA |
| Wood Frame | 6/8/2021 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 7/22/2021 | Partial Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/18/2021 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 8/18/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/18/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/18/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/20/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/20/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/20/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/25/2021 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/25/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/25/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/21/2021 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Rough | 12/21/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/21/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/23/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 12/23/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 1/4/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/16/2022 | Partial Approval | THOMAS LOGRASSO |