9118 W HARGIS ST 90034
Certificate Information: 9118 W HARGIS ST 90034
- Application / Permit
- 20014-30000-01611
- Plan Check / Job No.
- B20WL01698
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD with attached garage.
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/15/2020 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 5/28/2020 | TARIK SAOUD |
| Green Plans Picked Up | 6/5/2020 | APPLICANT |
| Applicant returned to address corrections | 11/18/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/16/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 1/8/2021 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 1/11/2021 | APPLICANT |
| Issued | 1/29/2021 | APPLICANT |
| CofO in Progress | 1/24/2022 | EVAN COOPER |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
| CofO Issued | 2/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 7/22/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2020 | JEANIE LAM |
| Sewer availability | Cleared | 7/23/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 10/4/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/5/2020 | JEANIE LAM |
| Trees in Parkway | Cleared | 11/10/2020 | JOHN KIM |
| Grading Pre-Inspection | Cleared | 12/16/2020 | JAHANSHAH POURHASSAN |
| GPI Written Notices | Cleared | 12/17/2020 | JAHANSHAH POURHASSAN |
Contact Information
| Architect | Musolino,, John Michael; Lic. No.: C33574 | 1200 OPAL STREET # 22 REDONDO BEACH, CA 90277 |
| Contractor | Owner-Builder | , |
| Engineer | Trevellin,, Maurizio; Lic. No.: C71368 | 707 ASHLAND AVE 2 SANTA MONICA, CA 90405 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/25/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 2/25/2021 | Partial Approval | EVAN COOPER |
| Sewer | 2/25/2021 | Approved | EVAN COOPER |
| Underground Mechanical | 2/25/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 3/16/2021 | Corrections Issued | EVAN COOPER |
| Deputy Steel/Welding | 3/31/2021 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | RYAN BARNES |
| BUILDING-Rough-Frame | 6/3/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 6/3/2021 | Approved | EVAN COOPER |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 6/3/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/3/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/3/2021 | Approved | EVAN COOPER |
| Wood Frame | 6/3/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 6/7/2021 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Approved | EVAN COOPER |
| Shower Pan | 6/7/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/7/2021 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 6/10/2021 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 6/10/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/16/2021 | Approved | EVAN COOPER |
| Green Building Rough | 6/16/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/16/2021 | Approved | EVAN COOPER |
| Wood Frame | 6/16/2021 | Approved | EVAN COOPER |
| Insulation | 6/22/2021 | Conditional Approval | AMY COLIN |
| Interior/Exterior Lathing | 6/22/2021 | Approved | AMY COLIN |
| Shower Pan | 6/22/2021 | Corrections Issued | AMY COLIN |
| Gas Test | 6/28/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/28/2021 | Approved | EVAN COOPER |
| Shower Pan | 6/28/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/22/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 10/22/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/29/2021 | Approved | EVAN COOPER |
| HVAC-Final | 10/29/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 11/29/2021 | Approved | EVAN COOPER |
| Final | 11/29/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 11/29/2021 | Approved | EVAN COOPER |
| Green Building Final | 11/29/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/29/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 11/29/2021 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 11/29/2021 | Approved | EVAN COOPER |
| Final | 1/24/2022 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 1/24/2022 | Approved | EVAN COOPER |